Law library · Sierra Leone · The Public-Private Partnership Act, 2010
Section 24: A PPP Agreement shall provide for–
Status not yet checkedThe Public-Private Partnership Act, 2010, Sierra Leone
(a) mechanisms and procedures for the transfer
of assets to a contracting authority in case
of a winding up;
(b) the compensation to which the private
partner may be entitled in respect of assets
transferred to a contracting authority or to a
new private partner or purchased by a
contracting authority;
(c) the transfer of technology required for the
operation of a PPP Project;
16 17
Termination
Agreement by
contracting
authority.
Termination
Agreement
by private
Termination
Agreement by
either party.
Compensation
upon
termination
Management
Agreements.
Winding up
and transfer
measures.
(d) the training of a contracting authority’s
personnel or of a successor private partner
in the operation and maintenance of the PPP
Project; and
(e) the provision, by the private partner, of
continuing support services and resources,
including the supply of spare parts, if
required, for a reasonable period after the
transfer of the PPP Project to a contracting
authority or to a successor private partner.
PART III–ESTABLISHMENT OF PUBLIC-PRIVATE
PARTNERSHIP COUNCIL
Read the whole lawDownload PDFAsk Tima what this means
Check the current official version before relying on this text. MiLAWYER shares legal information, not legal advice.