Section 43, The Public-Private Partnership Act, 2010
Status not yet checkedThe Public-Private Partnership Act, 2010, Sierra Leone
If the Council has given approval for a PPP Project toproceed to the procurement phase and a key assumption in the
feasibility study is materially revised after such approval, including
any assumption concerning affordability, value for money and
substantial technical, operational and financial risk transfer, the
contracting authority shall immediately–
(a) provide the Unit with details of the intended
revision including a statement regarding the
purpose and impact of the intended revision
on the affordability, value for money and risk
transfer evaluation contained in the
feasibility study; and
(b) provide the Unit with a revised feasibility
study for submission to the Council.