Law library · Sierra Leone · The Public-Private Partnership Act, 2010
Section 15, The Public-Private Partnership Act, 2010
Status not yet checkedThe Public-Private Partnership Act, 2010, Sierra Leone
(1) Without prejudice to section 15, a PPP Agreementshall set out the extent to which a private partner is entitled to a
revision of the PPP Agreement with a view to providing compensation
in the event that the cost of the private partner’s performance of the
agreement has substantially increased or that the value the private
partner receives for such performance has substantially diminished
as compared with the costs and the values of performance originally
foreseen , as a result of –
12 13
Security
interest.
Assignment
Transfer of
controlling
interest in
private
Operation of
Compensation
for specific
changes in
legislation.
Revision of
P P P
Agreement
(a) changes in economic or financial conditions;
or
(b) changes in legislation or regulations not
specifically applicable to the PPP Projects;
provided that the economic, financial,
legislative or regulatory changes
(i) occur after the conclusion of the PPP
Agreement;
(ii) are beyond the control of the private
partner; and
(iii) are of such a nature that the private
partner could not reasonably be
expected to have taken them into
account at the time the PPP Agreement
was negotiated or have avoided or
overcome their consequences.
(2) A PPP Agreement shall establish procedures for
revising the terms of the PPP Agreement following the occurrence of
the circumstances described in subsection (1).