Section 16, The Public-Private Partnership Act, 2010
Status not yet checkedThe Public-Private Partnership Act, 2010, Sierra Leone
(1) A contracting authority shall have the right, underthe prescribed circumstances set out in a PPP Agreement, to take
over the operation of a PPP Project, for the purpose of ensuring the
effective and uninterrupted delivery or timely completion of the PPP
Project in the event of a-
(a) material default by the private partner in the
performance of its obligations; and
(b) failure by the private partner to rectify the
breach within a reasonable period of time after
having been given notice by the contracting
authority to do so.
(2) The duration of a takeover referred to in subsection
(1) and the residual rights– (if any) of the private partner shall be as
set out in the PPP Agreement.
(3) When a contracting authority elects to take over a
PPP Project under subsection (1), the contracting authority, in
accordance with the terms of the PPP Agreement—
(a) shall collect and pay any revenues that are
subject to lien to satisfy any obligation;
(b) may develop and operate the PPP Project,
impose user levies and comply with any
existing service contract; and
(c) may solicit proposals, as appropriate, for the
construction, maintenance or operation of the