Law library · Sierra Leone · The Public-Private Partnership Act, 2010
Section 18, The Public-Private Partnership Act, 2010
Status not yet checkedThe Public-Private Partnership Act, 2010, Sierra Leone
The duration of a public private partnership shall be setout in the PPP Agreement, and the contracting authority may not
agree to extend its duration except as a result of the following
circumstances-
(a) delay in completion or interruption of
operation due to circumstances beyond the
reasonable control of either party;
(b) suspension of the PPP Project brought about
by acts of the contracting authority or other
public authority;
14 15
Takeover of
Substitution
of private
Duration and
extension of
PPP Agreement.
(c) an increase in costs arising from requirements
of the contracting authority not originally
foreseen in the PPP Agreement, if the private
partner would not be able to recover such
costs without such extension; or
(d) on agreement with the private partner, for
reasons of national or public interest, as
justified in the record to be kept by the
contracting authority.