Law library · Sierra Leone · The Public Procurement Act, 2004
Section 38, The Public Procurement Act, 2004
Status not yet checkedThe Public Procurement Act, 2004, Sierra Leone
(1) The open bid proceedings may include aprequalification stage or apply a post qualification procedure prior
to the award of contract.
(2) The open bid may be carried out in a single stage or in
two stages, but use of the two-stage method is appropriate in the
circumstances outlined in subsection (3); all other methods to be
selected as the circumstances require from this Part.
(3) An open bid may be held in two stages in the following
cases:–
(a) when it is not feasible to define fully the
technical or contractual aspects of the
procurement to elicit competitive bids; and
(b) when, because of the complex nature of the
goods, works or services to be procured, the
procuring entity wishes to consider various
technical or contractual solutions, and to
discuss with bidders about the relative merits
of those variants before deciding on the final
technical or contractual specifications.
Read the whole lawDownload PDFAsk Tima what this means
Check the current official version before relying on this text. MiLAWYER shares legal information, not legal advice.