Law library · Sierra Leone · The Public Procurement Act, 2004
Section 57, The Public Procurement Act, 2004
Status not yet checkedThe Public Procurement Act, 2004, Sierra Leone
(1) Where the bidding documents require the supplier orcontractor whose bid has been accepted to sign a written procurement
contract conforming to the bid, the procuring entity and the supplier
shall sign the procurement contract within 30 days after the notice
referred to in subsection (2) of section 56 has been dispatched to the
supplier or contractor.
(2) Where a written procurement contract is required to
be signed, the procurement contract shall enter into force when the
contract is signed by the supplier or contractor and by the procuring
(3) Except as provided in subsection (2) of section 56, a
procurement contract in accordance with the terms and conditions of
the accepted bid shall enter into force when the notice is dispatched
to the supplier or contractor that submitted the bid, if it is dispatched
while the bid is in force.
(4) Contracts shall be signed by the head of a procuring
entity, but he may delegate signature of small contracts to the head of
the procurement unit or other senior official of the entity.
Nondisclosure of
bid
evaluation
details.
Prohibition
of
negotiations.
Award of
Acceptance
of bid and
signature of
50 51