Law library · Sierra Leone · The Public Procurement Act, 2004
Section 64, The Public Procurement Act, 2004
Status not yet checkedThe Public Procurement Act, 2004, Sierra Leone
(1) Prior to the entry into force of a contract, applicationfor review shall be made, in the first instance, in writing, to the head
of the procuring entity.
(2) The head of the procuring entity shall not entertain
an application for review unless it was submitted within 14 working
days, or other deadlines set in the regulations, or when the bidder
submitting it became aware of the circumstances giving rise to the
complaint or when that bidder should have become aware of those
circumstances, whichever is earlier.
(3) Unless the complaint is resolved by mutual agreement,
the head of the procuring entity shall suspend the procurement
proceedings and shall, within five working days after submission of
the complaint, issue a written decision, stating the reasons, and, if
the complaint is upheld, indicating the corrective measures to be
taken.
(4) If the Head of the procuring entity does not issue a
decision within the time stated in subsection (3), or if the complainant
is not satisfied with the decision of the head of the procuring entity,
the complainant is entitled to submit a complaint to the Independent
Procurement Review Panel pursuant to section 65.
(5) Complaints under subsection (4) shall not be heard
unless submitted to the Independent Procurement Review Panel
within ten working days from the elapse of the time stated in subsection
(3) or from the date on which the entity’s decision was communicated
to the complainant.
Read the whole lawDownload PDFAsk Tima what this means