Law library · Sierra Leone · The Tonkolili Agreement Ordinance
Section 10, The Tonkolili Agreement Ordinance
Status not yet checkedThe Tonkolili Agreement Ordinance, Sierra Leone
(a) If at any time during the term of the Second Licence and/orthe Permanent Lease the Company after being requested so to do by the
Government shall fail to adduce reasonable proof that the reserves of
workable iron ore of good shipping quality within the Marampa Concession
are in quantity more than seven times the average of the quantity of annual
shipments from such Concession during the five calendar years immediately
preceding such request the Government may give notice in writing to the
Company requiring it within twelve months of the date of such notice to
commence construction of the railway extension and the Company shall
duly comply with such request save in case of force majeure or unless before
the expiration of such twelve months it agrees to surrender the Second
Licence or the Permanent Lease as the case may be. In the event of any
dispute as to whether or not the Company has adduced such reasonable proof
the same shall be referred to arbitration in accordance with Clause 27 of
this Agreement and the period of twelve months hereinbefore mentioned
shall not be deemed to commence until the conclusion of such arbitration.
(b) Subject as aforesaid the Company shall not be under any obligation
to commence construction of the railway extension.
(c) When and if the Company shall commence construction of the
railway extension it shall proceed with such construction so as to complete
the same within five years from the date of commencement save in the case
of force majeure or unless the Government shall consent to a prolongation
of the period of construction. Such consent shall not be unreasonably
withheld in the event of unforeseen difficulties arising.
(d) Failure by the Company to commence the construction of the
railway extension in accordance with the provisions of this clause save in
the case of force majeure shall entitle the Government to cancel the Second
Licence or the Permanent Lease as the case may be forthwith by notice in
writing to the Company to that effect. This right of cancellation shall not
extend to separate mining rights andfor mining leases which may have been
granted by the Government to the Company during the periods of the First
and/or Second Licence and/or the Permanent Lease under the provisions
of Clauses 3, 6 and 9 hereof or any rights or easements which at the date of
such cancellation are enjoyed with such separate mining rights andfor leases.
(e) The provisions of the Marampa Railway and Harbour Works
Construction Ordinance shall 1mdatis mutandis be made applicable to the
railway extension. All lands within and without the demised areas which
are required for the railway extension shall be acquired by the Company
under the provisions of that Ordinance.
(f) Where the term " force majeure " is used in this clause it shall be
deemed to include war or the anticipated imminence thereof between any
nations prohibition of shipment transport or import of iron ore civil
commotion political disturbances financial crises strikes lock-outs accidents
epidemics and any other event of any nature or kind whatsoever beyond
the personal control of the Company which directly or indirectly hinders
or prevents the Company from commencing or proceeding with the
construction of the railway extension.