Section 19, The Public Private Partnership Act, 2014
Status not yet checkedThe Public Private Partnership Act, 2014, Sierra Leone
A contracting authority on the authorisation of Cabinet ordelegated role to the PPP Unit may terminate a PPP Agreement-
(a) when it can no longer be reasonably expected
that the private partner will be able or willing
to perform its obligations, owing to
insolvency, material default or otherwise, as
agreed in the PPP Agreement; or
(b) for compelling reasons of national or public
interest, subject to payment of compensation
to the private partner, as agreed in the PPP
(c) as otherwise provided in the PPP Agreement.