MiLAWYER

Law library · Sierra Leone · Sierra Leone Electricity and Water Regulatory Commission Act 2011,

Section 11, Sierra Leone Electricity and Water Regulatory Commission Act 2011,

Status not yet checkedSierra Leone Electricity and Water Regulatory Commission Act 2011,, Sierra Leone

(1) The permit holder shall ensure that the generation plant – (a) meets the standards relating to specification and design; (b) is installed and operated by a qualified person and in accordance with good practice; (c) is installed at an appropriate location; (d) complies with environmental requirements. (2) An operator of a captive generation plant shall ensure that – (a) the generation plant and its associated facilities – (i) are operated and maintained in accordance with the manufacturer's manual; (ii) do not pose a danger to the public; and (b) the highest level of safety is observed. (3) Where the facilities are connected to an electricity network, the permit holder shall ensure that the generation plant and facilities are operated- Conditions of permit. (a) in accordance with the distribution or grid code; and (b) in a manner that prevents interference with the network.

Read the whole lawDownload PDFAsk Tima what this means

Check the current official version before relying on this text. MiLAWYER shares legal information, not legal advice.