(1) The permit holder shall ensure that the generation plant –
(a) meets the standards relating to specification
and design;
(b) is installed and operated by a qualified person
and in accordance with good practice;
(c) is installed at an appropriate location;
(d) complies with environmental requirements.
(2) An operator of a captive generation plant shall ensure
that –
(a) the generation plant and its associated facilities
–
(i) are operated and maintained in
accordance with the manufacturer's
manual;
(ii) do not pose a danger to the public;
and
(b) the highest level of safety is observed.
(3) Where the facilities are connected to an electricity
network, the permit holder shall ensure that the generation plant and
facilities are operated-
Conditions
of permit.
(a) in accordance with the distribution or grid
code; and
(b) in a manner that prevents interference with the
network.