Law library · Sierra Leone · Commission (Mini Grid ) Regulations, 2019
Schedule 1, Commission (Mini Grid ) Regulations, 2019
Status not yet checkedCommission (Mini Grid ) Regulations, 2019, Sierra Leone
Regulation 8 (1) a
Application form for basic mini-grid licence
IMPORTANT NOTES: Your application is incomplete unless
all required documents are submitted.
SLEWRC reserves the right to verify the
accuracy of this information.
The basic mini-grid licence, if approved by SLEWRC Commission,
will be valid for a duration up to 10 years and may be renewed or
extended by the Commission beyond that time following procedure
described in these Regulations.
In compliance with the SLEWRC Mini-Grid Regulations, 2019I
_________________[name of representative] certify that, [name of
company] ____________________________________ is
intending to construct, install or start to operate a mini-grid system
with distribution power not more than 100 kW of distributed power
on [date] __________________ and hereby applies for a basic minigrid licence pursuant to the SLEWRC Mini-Grid Regulations, 2019.
Penalty.
1.0 PARTICULARS OF APPLICANT AND CONTACT PERSON
Name of applicant:........................................................................................
Physical address:.........................................................................................
Postal address:.................................................................................................
Tel:...................................................................................................................
Fax:.....................................................................................................................
Mobile phone:................................................................................................
E-mail:.............................................................................................................
Website address:............................................................................................
Name of contact person:.............................................................................
Mobile phone of contact person:.................................................................
E-mail for contact person:...............................................................................
2.0 LEGAL STATUS OF APPLICANT
2.1 Indicate legal status of Applicant (Tick relevant option)
A. Sole proprietorship
B. Partnership
C. Cooperative society
D. Company Limited by Shares
E. Other (please specify)
2.2 List and particulars of directors:
Name Nationality Address Expiry date of tenure
3.0 NATURE OFAPPLICATION
3.1 State whether application is a new application or amended application.
3. 2 Existing Licence
Does the applicant have an existing basic or full mini-grid licence issued by the
commission for other systems?
If yes, state the nature of the licence, date issued and the licence number.
3.3 Refusal, suspension or Cancellation of Licence
Has the applicant ever been refused a licence or had its licence suspended and/or
cancelled by the Commission?
If yes, give details of the refusal, suspension, and/or cancellation.
4.0 MAIN BUSINESS ACTIVITIES OF APPLICANT
Please indicate the main business activities the applicant is currently engaged in.
5. 0 DESCRIPTION OF PROJECT
5.1 Site of the mini-grid
Village: Ward:
Town: City:
Chiefdom: District:
5. 2 Generation
Solar ............... kW
Generation Wind ............... kW
Biomass ............... kW
Hydro ............... kW
Diesel ............... kW
Other: ............. ............... kW
Total: ............... kWh
Storage ......................... ............... kWh
Inverters ............................... ...............kW
Terminal Voltage ..........................V
Rated Frequency .......................... Hz
Expected Annual Generation
(kWh/year), ......................... kWh/year
Location of the power plant (geographical coordinates / GPS):
Is the power plant new? If no, please state number of years the plant has been in
operation. If yes, please state the expected date of commissioning.
5.3 Distribution
Lines Three-phase MV ............ metres
Single phase LV ............ metres
Three-phase LV ............ metres
Total: ............ metres
Type of Lines Overhead Underground
Concrete ............ poles
Wood ............ poles
Poles Steel ............ poles
Other: ............ ............ poles
Total: ............ poles
............... type
Transformers ............... kVA
............... number
Length of distribution network (indicate geographical coordinates of four reference
points)
5.4 Consumers
Number of consumers:
Residential:........................................ Commercial:......................
Productive/Industrial: ...................... Health Centres:................
Schools:...................... Street lighting: .................
Other (please specify):................................................................................
5.5 Electricity Sales
Expected electricity sales [kWh/year, or number of flat rate, or power
price]:...............................................
Indicated average electricity tariff [SLL/kWh or flat rate, or per W]:..........................
6.0 DECLARATION BY THE APPLICANT
The project is not unlawful or contrary to the interest of Sierra Leone, the National
Electricity Act, 2011, the SLEWRC Act, 2011 and relevant SLEWRC Regulations. I/
we hereby declare that the details stated above are, to the best of my/our knowledge,
true and correct.
Datedthis....................................day of ........................................................20..................
THE COMMON SEAL OFTHE WITHIN NAMED APPLICANT
Name of Applicant Signature
Has hereunto been affixed in the presence of:
Sign: Sign:
Name: Name:
Designation: Designation:
Sworn to this........................ day of........................ 20...... at...........................................
ACCOMPANYINGDOCUMENTATION
1. Completed application form
2. Map with position of power station and distribution network marked using
indicators to distinguish low voltage single phase and three phase as well
as medium voltage networks
3. Certified copy of business registration or certificate of incorporation,
4. Memorandum and articles of association, deed of partnership or deed of
trust, as applicable,
5. Tax & NASSIT registration certificates
6. Proof of technical qualification of electrician (e.g. certificate)
7. A 3 - 5 years Business plan
FOR OFFICIAL USE ONLY
1. Date of receipt of application:.........................................................................
2. Fees paid and receipt number:........................................................................
3. Results of verification for completeness:.....................................................
4. Recommendation of SLEWRC Legal Division:............................................
5. Recommendation of SLEWRC Head of Electricity:......................................
6. Decision of SLEWRC:.......................................................................................
7. Issue date of licence:.........................................................................................
8. Expiration date of licence: .................................................................................
9. Other relevant information: ...............................................................................