Section 62, The Public Procurement Act, 2016
Status not yet checkedThe Public Procurement Act, 2016, Sierra Leone
(1) The contract may be negotiated with the selectedconsultant but negotiations may not be simultaneously held with
several consultants.
56 57
Selection or
based on
quality.
Contract
award.
Selection
based on
quality and
cost.
(2) The procuring entity shall notify its proposed award
to all short-listed consultants at the same time it notifies the selected
consultant, but where the value of the contract exceeds the levels set
out in the regulations, the contract shall not be signed until at least
14 calendar days have passed following the giving of that notice.
(3) The selected consultant shall not be permitted to
substitute key staff, unless both parties agree that undue delay in
the selection process makes such changes unavoidable or that such
changes are critical to meet the objectives of the assignment.
(4) The key staff proposed for substitution shall have
qualifications equal to or better than the key staff initially proposed.
PART VII –COMPLAINTS PROCEDURE