- Preamble
- Section 1
- Section 2 — In this Act, unless the context otherwise requires–
- Section 3
- Section 4
- Section 5
- Section 6
- Section 7
- Section 8
- Section 9
- Section 10
- Section 11
- Section 12
- Section 13
- Section 14
- Section 15
- Section 16
- Section 17
- Section 18
- Section 19
- Section 20
- Section 21
- Section 22
- Section 23
- Section 24
- Section 25 — (1) A bid may be rejected only in accordance with this
- Section 26
- Section 27
- Section 28
- Section 29
- Section 30
- Section 31
- Section 32
- Section 33
- Section 34
- Section 35
- Section 36
- Section 37
- Section 38
- Section 39
- Section 40
- Section 41
- Section 42
- Section 43
- Section 44
- Section 45
- Section 46
- Section 47
- Section 48
- Section 49
- Section 50
- Section 51
- Section 52
- Section 53
- Section 54
- Section 55
- Section 56
- Section 57
- Section 58
- Section 59
- Section 60
- Section 61
- Section 62
- Section 63
- Section 64
- Section 65
- Section 66 — (1) Subject to sub-section (3) of section 5 of the National
- Section 67 — (1) Disposal of obsolete or surplus items shall be by–
- Section 68
- Section 69 — (1) The Public Procurement Act, 2004 is hereby repealed.
- First Schedule
THE PUBLIC PROCUREMENT ACT, 2016
Being an Act to make provision for the continuance in
existence of the National Public Procurement Authority, to further
regulate and harmonise public procurement processes in the public
service, to decentralize public procurement to procuring entities, to
promote economic development, including capacity building in the
field of public procurement by ensuring value for money in public
expenditures and the participation in public procurement by qualified
suppliers, contractors, consultants and other qualified providers of
goods, works and services and to provide for other related matters.
[ ]
ENACTED by the President and Members of Parliament in this
present Parliament assembled.
Date of commencement.
SIGNED this 11th day of February, 2016.
DR. ERNEST BAI KOROMA,
President.
LS
PART I – PRELIMINARY
(1) This Act shall apply to the procurement of goods, worksand services, including any procurement financed in whole or in part
from public or donor funds by the following bodies or organizations-
(a) Government Ministries, departments and
agencies;
(b) local councils;
(c) sub-vented agencies;
(d) state-owned enterprises which utilise public
funds;
(e) universities, colleges, hospitals, companies
and other institutions which are wholly
owned by the State or in which the State has
at least 25% interest; and
(f) any entity in the private sector which is given
the responsibility for carrying out activities
using public funds.
(2) Where this Act conflicts with the procurement rules
of a donor or funding agency, the application of which is mandatory
pursuant to or under an obligation entered into by the Government
of Sierra Leone, the rules of the donor or funding agency shall prevail;
but in all other respects, procurement shall be governed by this Act.
(3) Where the Minister responsible for defence or
national security, with the approval of the Defence Council,
determines that a procurement related to national defence or national
security requires the application of special measures, the application
of the rules and procedures set out in this Act may be modified by the
National Public Procurement Authority, but the modification shall be
governed only by defence or national security considerations.
(4) For the purposes of subsection (3), procurement of
items such as general stores, uniforms, stationery, office equipment
and standard vehicles shall not be classified as national defence or
national security procurement.
(5) In implementing this Act, including the composition
of boards, committees and other organs provided therein, regard
shall be had to compliance with the Government’s policy of promoting
the appointment and full participation of women.
“Authority” means the National Public Procurement
Authority referred to in section 3;
“bid” means, a proposal or quotation submitted by a
bidder in response to an invitation by a procuring
entityaccording to the type of procurement method
being used, ;
“bid security” means the bank guarantee or other form
of security submitted by a bidder together with a bid
to secure the obligations of the bidder participating
in a bidding proceeding, including the obligation to
sign a procurement contract if the bid is accepted, in
accordance with the requirements of this Act and
the bidding documents;
“Board” means the Board of the Authority;
“collusive practices” means a scheme or arrangement
between two or more parties with or without the
knowledge of the procuring entity, designed to
establish prices at artificial, noncompetitive levels;
“consultant” means the provider of intellectual
services, including consultants’ services;
“contract” means an agreement between a procuring
entity and supplier, contractor or consultant resulting
from procurement processes;
2 3
Application.
Interpretation.
“contractor” means a natural or legal person under
contract with a procuring entity to be a provider of
civil works;
“corrupt practice” means, corrupt practice as defined
in the Anti-Corruption Act;
“employer” means the contracting party benefiting
from a works contract (usually the procuring entity);
“force account” means the conduct of procurement
proceedings by any procuring entity with selfsupervision, utilising the entity’s own resources;
“fraudulent practice” means a misrepresentation or
omission of facts in order to influence a selection
process or the execution of a contract;
“goods” means objects of every kind and description,
including commodities, raw materials, products and
equipment, and objects in solid, liquid or gaseous
form, and electricity, as well as services incidental to
the supply of the goods, if the value of those
incidental services does not exceed that of the goods
themselves;
“head of procuring entity” means the chief executive
officer of the entity such as the Minister of a Ministry
or the overall head of a procuring entity;
“Independent Procurement Review Panel” means the
Independent Procurement Review Panel established
by section 20 for the purpose of conducting
independent administrative review of challenges
to award decisions and complaints arising under this
Act;
“interest” means, any Government Stake, Share,
Portion, Claims investment, stock or equity in any
institution;
4 5
“intellectual services” means any activity of an
intellectual nature that does not lead to a measurable
physical output;
“performance security” means the bank guarantee or
other form of security submitted by the supplier,
contractor or consultant to secure their obligations
under the procurement contract, in accordance with
the requirements in the bidding documents;
“member” means a member of the Board;
“Minister” means the Minister responsible for finance:
“procurement” means the acquisition by any
contractual means of goods, works, intellectual
services or other services;
“procurement committee” means the group within the
procuring entity, comprising officials within and
outside of the entity, referred to in section 18;
“procuring entity” means any organ of the State or
regional and local authorities as well as statutory
bodies, public sector corporations which are majority
owned by the Government, public utilities using
revenue collected by the sale of public services, as
well as any other natural or legal person to whom
public funds have been allocated for use in public
“procurement unit” means the department formally
established within the procuring entity to carry out
the procurement activities of that entity in
accordance with the functions set out in section 19;
“public funds” means any monetary resources of the
State budget, or aid and credits under agreement
with foreign donors, or extra-budgetary resources
of procuring entities, used in public procurement;
“public office” means, public office as defined in the
constitution of Sierra Leone;
“public officer” means,public officer as defined in the
Constitution of Sierra Leone;
“regulations” means the regulations issued by the
National Public Procurement Authority to fulfill the
objectives and to carry out the provisions of this
Act;
“services” means any services other than intellectual
services;
“supplier” means a natural or legal person under
contract with a procuring entity to supply goods,
construct works or provide intellectual and other
services;
“vote controller” means Permanent Secretary of a
Government Ministry, Chief Administrator of a local
council, Managing Director or a General Manager,
Executive Director or other head of a State-owned
enterprise, or head of a Government department,
agency or commission;
“works” means all works associated with the
construction, reconstruction, demolition, repair or
renovation of a building, structure or works, such as
site preparation, excavation, erection, building,
installation of equipment or materials, decoration and
finishing, as well as services incidental to
construction such as drilling, mapping, satellite
photography, seismic investigations and similar
services provided pursuant to the contract, if the
value of those services does not exceed that of the
construction itself.
PART II – ESTABLISHMENT AND FUNCTIONS OF
NATIONAL PUBLIC PROCUREMENT AUTHORITY
(1) Subject to this Act, there is hereby continued inexistence, the body which immediately before the commencement of
this Act, was known as the National Public Procurement Authority.
(2) The Authority shall be a body corporate having
perpetual succession and capable of acquiring, holding and disposing
of any property, whether movable or immovable, and of suing and
being sued in its corporate name and, subject to this Act, of performing
all such acts as bodies corporate may by law perform.
(3) The Authority shall have a common seal, the use of
which shall be authenticated by the signatures of –
(a) the Chairman or other member of the Board
authorised either generally or specially by
the Board in that behalf; and
(b) the Chief Executive or some other person
authorised by the Board in that behalf.
(1) The governing body of the Authority shall be a Boardconsisting of–
(a) the Chairman, who shall be a person
competent and knowledgeable in public
procurement and the public service;
(b) a representative of the Attorney-General and
Minister of Justice and the Chief Executive
who shall be Ex-Officio members.
(c) five persons appointed for their knowledge
and experience in public procurement and the
public service, of whom two shall represent
public sector interests and three shall
represent the broad cross-section of the
private business community and professional
associations of which two shall be women;
6 7
Continuance
of National
Public Procurement
Board of
(2) The Chairman and members refered to under
paragraph (c) of sunsection (1) shall be appointed, appointed by the
President and subject to the approval of Parliament.
(1) The Chairman and other members of the Board referedto in paragraph (c) of subsection (1) of section 4 shall hold office for
a term of three years and shall be eligible for reappointment for another
term of three years.
(2) A person shall cease to be a member of the Board on
any of the following grounds–
(a) for his inability to perform the functions of
his office by reason of infirmity of mind or
body;
(b) for proven misconduct;
(c) if he becomes bankrupt or insolvent;
(d) if he is convicted of an offence involving
fraud or dishonesty;
(e) if he fails to attend three consecutive
meetings of the Board without reasonable
cause;
(f) if he resigns his office by written notice to
the Minister.
(g) after serving two terms.
(1) Subject to this Act, the Board shall have the controland supervision of the Authority.
(2) It shall also be the responsibility of the Board to
provide policy guidance and advicethat will secure the efficient
implementation of the functions of the Authority and enhance the
overall performance of the Authority.
The Chairman and the other members of the Board and anyperson co-opted by the Board under subsection (5) of section 9
shall be paid such remuneration, fees and allowances as the Board
may determine, with the approval of the Minister.
(1) Where the Chairman or a member of the Board dies,resigns, is removed from office or is absent from Sierra Leone for a
continuous period exceeding three months or is by reason of illness
unable to perform the functions of his office–
(a) the members of the Board shall, as the case
may be elect one of their number to act as
Chairman until such time as the Chairman
resumes his office or another is appointed in
his stead; and
(b) subject to this Act another member shall be
appointed.
(2) Where a person is elected as Chairman or appointed
as a member to fill a vacancy, he shall hold office for the remainder of
the term of the previous Chairman or member, as and shall, subject to
thisAct, be eligible for re-appointment.
(1) The Board shall hold its first meeting on such dateand at such place as the Minister, after consultation with the Board,
may determine; and thereafter, the Board shall meet for the dispatch
of business at such time and place as the Chairman may decide but
shall meet at least once every month.
(2) At any meeting of the Board where he is present, the
Chairman shall preside and, in his absence, the members present may
elect one of their number to preside.
(3) The quorum at a meeting of the Board shall be four,
including the Chief Executive.
8 9
Remuneration
of members.
Tenure of
members of
Functions of
Filling of
vacancies.
Meetings of
(4) Each member including the Chief Executive shall have
one vote but in the case of an equality of votes, the Chairman shall
have a casting vote.
(5) The Board may at any time co-opt any person to
provide special or additional technical knowledge or advice otherwise
assist the Board at any of its meetings but the person co-opted shall
not vote on any matter for decision by the Board.
(6) All acts, matters or things authorised or required to
be done by the Board shall be decided at a meeting where a quorum
is present and the decision is supported by the votes of at least four
members, including the Chairman.
(7) Any proposal circulated among all members and
agreed to in writing by a two-thirds majority of all members shall be of
the same force or effect as a decision made at a duly constituted
meeting of the Board and shall be incorporated in the minutes of the
next succeeding meeting of the Board:
Provided that, if a member requires that such proposal be placed
before a meeting of the Board, this subsection shall not apply to
such proposal.
(8) The Board shall cause minutes of all its meetings to
be taken by the Secretary to the Board and signed by the Chairman
and kept in the proper form as a public document.
(9) Subject to this Act, the Board shall regulate its
meetings and procedure as it thinks fit.
A member of the Board who has any interest, direct orindirect, in any matter to be considered by the Board, shall disclose
the nature of his interest to the Board in such form as the Authority
may prescribe and shall also be recorded in the minutes of the Board
and such member shall not take part in any deliberation or decision
of the Board relating to that matter; and a member who contravenes
this section shall be guilty of misconduct and liable to be removed
from the Board.
In the discharge of its functions under this Act, the Boardmay –
(a) direct the Chief Executive to furnish it with
any information, reports or other documents
which the Board considers necessary for the
performance of its functions;
(b) give instructions to the Chief Executive in
connection with the management and
performance of the functions of the Authority.
(c) on the recommendation of the Chief
Executive, approve such organisational
structures as the Chief Executive may
consider necessary for the discharge of the
functions of the Authority.
(1) The Authority shall have a Secretariat which shallprovide administrative, secretarial and other support for the Authority
and shall have structures and organisation as the Authority may
consider necessary for the efficient performance of its functions.
(2) The Secretariat shall be headed by the Chief Executive
who shall be assisted by a Deputy both of whom shall be appointed
by the President subject to the approval of Parliament.
(3) In addition to the Chief Executive, the Secretariat shall
have such other staff as are required for the efficient performance of
the functions of the Authority.
(4) As head of the Secretariat, the Chief Executive shall
be responsible to the Authority for–
(a) the day-to-day management of the affairs of
the Authority
10 11
Powers of
Disclosure of
interest.
Secretariat of
(b) the administration, organization and control
of the other staff of the Authority;
(c) the management of the funds and other
property of the Authority;
(d) the performance of such other functions as
the Authority may determine.
(5) The other staff of the Authority, shall be appointed
by the Board upon such terms and conditions as shall be determined
by the Board.
(6) The activities of the Authority shall be financed by a
fund consisting of–
(a) moneys appropriated for the purposes of the
Authority by Parliament;
(b) grants made to the Authority by any agency
or authority.
(c) retention from fines.
(7) The Authority shall keep proper books of accounts and
proper records in relation thereto and such accounts, books and
records shall be in the form approved by the Auditor-General.
(8) The financial year of the Authority shall be the same as the
financial year of the Government.
(9) The books and accounts of the Authority shall each year be
audited by the Auditor-General or by an auditor appointed or
authorized by the Auditor-General, who shall submit a report on each
audit to the Authority.
(1) The Chief Executive shall, within three months afterthe end of each financial year, submit for the approval of the Board an
annual report of the activities, operations, undertakings, property
and finances of the Authority for that year.
(2) Subject to subsection (1), an annual report shall
include a copy of the audited accounts of the Authority with the
audit report thereon.
(3) A copy of the annual report approved by the Board
shall be sent to the Minister not later than six months after the end of
the year to which the report relates and the Minister shall as soon as
possible, but not later than one month of the receipt thereof, lay the
report before Parliament.
(1) The object for which the Authority is established isto regulate and monitor public procurement in Sierra Leone and to
advise the Government on issues relating to public procurement.
(2) Without prejudice to the generality of subsection (1),
it shall be the responsibility of the Authority to–
(a) formulate policies and standards on public
procurement and to ensure compliance
therewith by all parties to procurement
contracts;
(b) assess the operations of the public
procurement processes and submit proposals
for the improvement of the processes,
including the introduction of information and
communications technology, and the
development of modalities for appropriate
collaboration among procuring entities;
(c) ensure capacity building and human resource
development for public procurement,
including development, promoting and
supporting training and professional
development of persons engaged in public
12 13
Annual
reports of
Functions of
(d) develop and recommend to heads of
procuring entities a career development and
management programme, and a system for
selection, appointment and termination of
appointment of procurement officers;
(e) disseminate information about, and promote
awareness of the public procurement
system;
(f) issue standard forms of contract and
standard bidding documents for mandatory
use by all procuring entities;
(g) provide interpretation of this Act and other
instructions governing the procurement
process;
(h) plan and coordinate technical assistance in
the field of public procurement;
(i) publish a quarterly Public Procurement
Bulletin which shall contain information on
public procurement, including approved
procurement plans, proposed procurement
notices, and notices of invitation to bid and
contract award information;
(j) publish in the Public Procurement Bulletin or
in the Gazette or newspaper with wide national
circulation or the electronic media, a database
of suppliers, contractors and consultants,
and records of prices to assist in the work of
procuring entities;
(k) on its own motion or based on reports by a
procuring entity or the Panel, or interested
parties, investigate and suspend from
procurement practice under this Act,
suppliers, contractors and consultants who
have neglected their obligations under a
procurement contract, or provided false
information about their qualifications,
contravened tax regulations, or offered
inducements referred to in this Act.
(l) maintain and issue on a regular basis to all
procuring entities a list of suspended
suppliers, contractors and consultants;
(m) prepare an annual report on the overall
functioning of the public procurement
system, including a profile of procurement
activities, to be presented to Cabinet and
tabled before Parliament through the Minister
of Finance;
(n) share information and cooperate with other
arms of Government to facilitate the
implementation of Government policies;
(o) conduct, at least annually, a procurement
forum bringing together public sector, private
sector, civil society and development partners
to address issues related to public
(p) pursuant to its monitoring function the
Authority shall institute–
(i) procurement review during the tender
preparatory and unto the evaluation
process;
(ii) contract reviews in the course of
execution of an awarded tender; and
14 15
No. 1 Public Procurement Act 2016No. 1 Public Procurement Act 201616 17
(iii) Performance reviews after the
completion of the contract in respect of
any procurement as may be required.
(q) perform such other functions as are incidental
or conducive to the attainment of the object
stated in subsection (1).
(3) Subject to sections 41, 42, 43, 44, 45, and 46 of this
Act, the Authority may endorse and give approval for the use by a
procurement committee, of a procurement method or methods, other
than competitive bidding, where the procurement requirement of the
procuring entity, in the opinion of the Authority, merits such
endorsement and approval.
(4) Nothing in the functions of the Authority under
subsections (1) , (2) and (3) shall be construed to include the power
to participate in the award of any specific procurement contract.
(5) In the performance of its functions under this Act the
Authority shall not be subject to the direction or control of any
person or authority.
(6) Notwithstanding anything to the contrary in any other
law, the Authority shall, after conducting an investigation and is
reasonably satisfied that there is a breach of this Act or any regulation
made under it–
(a) direct the procuring entity to take such
actions as are necessary to rectify the
contravention; or
(b) terminate the procurement processes.
(7) The Authority shall prior to making a decision, under
paragraph (b) of subsection (6), give the procuring entity and any
other person whom it believes that his legal right may be adversely
affected by the decision an opportunity to make representations.
(8) The Authority shall, where it finds persistent or
serious breach of this Act or regulations or guidelines made under it,
recommend to the competent authority–
(a) the suspension of funds disbursements to
any procurement financed by specific public
funds where a breach has been established
to entities;
(b) the disciplining of the accounting officer,
chairman or member of the procurement
committee or any other officer concerned with
the procurement process in issue.
(9) The Authority shall incur no liability towards the
procuring entity or any other person or body interested in the tender
under review or investigation by virtue of properly invoking its powers
under this section.
(1) The Authority shall have powers, in performing itsfunctions under this Act to–
(a) require any party to a procurement contract
by notice in writing to furnish in such form
and manner and within such time as may be
specified in the notice, periodical or other
information, estimates or returns concerning
such contract or such other matters as may
be specified in that notice;
(b) interview any party to a procurement contract
and require him to furnish such particulars
as the Authority may require;
(c) require a party to a procurement contract by
notice in writing to complete a form contained
in the notice with particulars relating to the
contract or such other matter specified in
the notice and to return it in the manner and
within the time specified therein.
Power to
obtain
information.
(2) A notice referred to in subsection (1) –
(a) may be served by delivering it to the party to
whom it is addressed or by sending it by
registered post, fax or e-mail to his last known
address by thee (3) publication in a widely
read news paper;
(b) shall state that it is served in exercise of the
powers conferred by this section and shall
include a general statement of the purpose
for which the information, estimates, returns
or particulars are required.
(3) When a requirement to furnish information, estimates,
returns or particulars under this Act is made, the information, estimates,
returns or particulars shall be furnished by the party concerned or a
person specifically authorised for the purpose by that party.
(4) Subject to this section, every party to a procurement
contract shall, to the best of his knowledge and belief, answer when
so required, all questions put to him orally or in writing by the Chief
Executive or an officer of the Authority authorised in that behalf, not
later than the date specified in the notice.
(5) A party to a procurement contract who–
(a) fails to answer a question put to him as
required under this Act or furnishes an
answer to such a question which is false or
misleading in any material respect, knowing
the answer to be false or misleading; or
(b) wilfully obstructs the Chief Executive or any
officer or employee of the Authority in the
performance of any of its functions under
this Act,
commits an offence and shall be liable on conviction to a fine not
less than Ten million Leones, or to imprisonment for a term not less
than twelve months or to both such fine and imprisonment.
(1) Notwithstanding any law to the contrary, no return orother commercially sensitive information collected by the Authority
under section 15 shall, subject to subsection (2), be disclosed to any
person.
(2) The return or other information referred to in
subsection (1) may, subject to the directions of the Chief Executive,
be disclosed–
(a) to any person if required for the performance
of that person’s functions under this Act;
(b) if required by any law or as evidence in any
court of law.
(3) Any officer of the Authority who in the course of his
employment under this Act–
(a) wilfully discloses any classified information
or data attained in the cause of such
employment to a person not authorised to
receive that information.
(b) uses information obtained in the course of
such employment for the purpose of
speculating in any stock, bond or other
security or any goods or services, before its
release is authorised by the Chief Executive;
or
(c) otherwise contravenes this section,
commits an offence and shall be liable on conviction to a fine not
less than Ten million Leones or to imprisonment for a term not less
than twelve months or to both such fine and imprisonment.
Confidentiality
and prohibition of
disclosure of
information.
18 19
PART III – PROCUREMENT COMMITTEES AND
PROCUREMENT UNITS
(1) Procurement-related functions shall be carried out byprocurement persons trained and knowledgeable in accordance with
the guidelines and qualification requirements established by the
(2) Subject to this Act, the procuring entity, including its
concerned officials, shall be responsible for procurement with the
funds at its disposal.
(3) The procuring entity shall not commence a
procurement activity for which funds are not available or for which
the Ministry or supervising authority has not issued a written
confirmation of budgetary allocation that the required funds shall
be made available in a timely manner and in the amount required
(1) A procurement committee shall be established in everyprocuring entity.
(2) The procurement committee shall be appointed by
the head of the procuring entity and its composition shall be in
accordance with subsection (9).
(3) A procuring entity shall be responsible, and vote
controllers and other officials concerned accountable, for public
procurement in accordance with this Act and any other enactments
which may be applicable.
(4) The head of a procuring entity shall appoint a staff
member of the entity to act as secretary to the procurement committee,
if the entity does not have a procurement unit.
(5) The secretary to the procurement committee shall take
minutes of meetings of the procurement committee and maintain a file
of all matters considered by the procurement committee.
(6) A procurement committee may delegate to a
procurement unit, authority to make contract award decisions, subject
to such decisions being subsequently reported to and recorded in
the minutes of the procurement committee.
(7) Delegation of the authority shall be expressed in terms
of estimated maximum contract values, which may differ according to
whether the contract is for procurement of goods, works or services.
(8) A procurement committee shall make necessary
arrangements to ensure that timely information on the execution and
conclusion of contracts by a department or division of a procuring
entity, as well as on supplier, contractor or consultant performance is
reported to the procurement committee.
(9) A procurement committee shall consist of the
following five members:–
(a) the vote controller, who shall act as the
Chairman;
(b) one senior official of the entity;
(c) the head of finance, accounts or any budget
professional;
(d) the head of the procurement unit, who shall
also be secretary to the committee;
(e) a representative of the concerned end-user
department, who shall be a rotating member.
(10) Additional rotating members may be drawn to provide
necessary technical legal and business expertise to the procurement
committee.
(11) The quorum for a meeting of a procurement committee
shall be three, comprising the Chairman and at least two other members
referred to in subsection (9).
committees.
staff to be
trained.
20 21
(12) Procurement committees may appoint technical
evaluation committees and advisers to assist the procurement unit in
bid opening procedures, bid evaluation and making recommendations
for award.
(13) The functions of a procurement committee shall
include–
(a) verification and approval of proper
procurement planning and preparation of
procurement processes carried out by the
procurement unit;
(b) consideration and approval of the draft
advertisements and other bidding documents
prepared by the procurement unit;
(c) review and approval of evaluation reports and
contract award recommendations, in cases
of procurement beyond the authorised limits
of the respective procurement unit;
(d) rejection of unsuccessful bids;
(e) approval of contracts with a value above the
authorised limits of the respective procurement unit;
(f) approval of applications for contract
modifications in the following cases–
(i) where the original contract award was
subject to procurement committee
approval;
(ii) where the value of the modification
exceeds the authorised limits applicable
to the procurement unit;
(iii) where the contract modification would
cause the total contract value to exceed
the authorised limits applicable to the
procurement unit;
(g) reporting of procurement activities to the
Authority;
(h) submitting annually updated databases of
suppliers, contractors and consultants, and
records of prices of the Authority for
publication; and
(i) such other functions as may be conferred
by any other enactment.
(14) Procurement committees may, upon approval by the
Authority, establish subsidiary procurement committees in district
offices of the procuring entity.
(1) A procurement unit shall be established in eachprocuring entity, staffed with persons trained and knowledgeable in
procurement and charged with carrying out, on a continuous basis,
functions related to procurement.
(2) Procuring entities shall ensure that the procurement
units referred to in subsection (1) are established and provided with
adequate staffing and resources.
(3) The functions of procurement units shall include–
(a) planning of procurement;
(b) preparation of invitations to bid and of
bidding documents;
(c) publication and distribution of invitations to
bid;
units.
22 23
(d) receiving and safeguarding of bids;
(e) conducting bid opening procedures;
(f) evaluation of bids, including management of
necessary technical evaluation committees
and advisers to properly evaluate the bids;
(g) performance of secretarial services for the
respective procurement committee;
(h) administering the implementation and
monitoring of contracts, to the extent that is
not carried out by end-user departments;
(i) assessment of the quality of the procured
goods, works and services;
(j) sourcing and profiling of all suppliers,
contractors and consultants, and the
maintenance of a database for that purpose;
(k) such other functions as may be conferred by
any other enactment.
(4) Appointment of staff of procurement units shall be
subject to continuing professional education requirements certified
and approved by the Authority.
(5) Procuring entities may establish subsidiary
procurement units for subdivisions of the procuring entity, which
shall–
(a) be located in the provinces;
(b) have a particularly large or specialised
procurement workload;
(c) operate in practice as an independent entity;
(1) There is hereby established a body to be known asthe Independent Procurement Review Panel, referred to in this Act
as “the Panel”, for the purpose of conducting independent
administrative review of challenges to the process of the award of
decisions and complaints arising out of this Act.
(2) The Panel shall consist of –
(a) a Chairman and two other members appointed
by the Minister from among eminent Sierra
Leoneans with a background in public
procurement or public private partnership,
the business community, university, the legal
profession and other relevant fields;
(b) the Attorney-General and Minister of Justice;
and
(c) the Executive Secretary, Sierra Leone Chamber
of Commerce, Industry and Agriculture.
(3) The Quorum shall be three members
(4) The members of the panel refered to in paragraph (a)
of subsection (12) shall hold office for a term of three years, but may
be re-appointed for a further term of three years only.
(5) Where a person is appointed as a mamber to fill a
vacancy he shall hold office for the remainder of the term of the
previous member and shall, subjected, to this Act, be eligible for
reappointment for another term of three years.
(6) The Panel may engage the services of such
consultants and advisers, or co-opt persons with specialized expertise
as it may require for the proper and efficient discharge of its functions
and such persons shall not have any voting power in decision making.
(7) The Minister shall appoint a secretary to the panel
who is suitably experienced and trained in the legal discipline to
carry out its administrative work and facilitate the conduct of its
business and the Secretary shall attend all the meetings of the panel
but shall have no voting rights.
Independent
Review Panel.
24 25
(8) All persons involved in public procurement under this
Act, shall when required to do so by the Secretary provide all necessary
information and data.
PART IV – GENERAL PROVISIONS ON PROCUREMENT
PROCESSES
(1) In order to be awarded a contract, or, if prequalificationprocesses are being held, in order to participate in the procurement
processes, a bidder must qualify by meeting the criteria set by the
procuring entity, which may include–
(a) professional and technical qualifications;
(b) equipment availability;
(c) past performance;
(d) after sales service;
(e) spare parts availability;
(f) legal capacity;
(g) financial resources and condition;
(h) professional records;
(i) assessment by the National Revenue
Authority to ascertain payment of taxes; and
(j) payment of social security contributions.
(2) The qualification criteria set out under subsection (1)
shall be applied by examining, through investigation and collaboration
with other Government agencies, whether the bidder does or does
not meet the qualification criteria and not by using a point system for
comparing the relative level of qualifications of participating bidders.
(3) The procuring entity shall be entitled to demand from
potential bidders and applicants for prequalification documentation
reflecting their qualification data.
(4) Any requirement established pursuant to this section
shall be set forth in the prequalification documents, if any, and in the
bidding documents, and shall apply equally to all bidders without
discrimination; and only those criteria stated in such documents shall
be applied.
(5) A procuring entity may disqualify a bidder if it finds
at any time that the information submitted concerning the
qualifications of the bidder was materially inaccurate or materially
incomplete.
(6) In order to identify persons that are qualified, prior to
the invitation of bids, prequalification shall be used for –
(a) procurement of large complex works in which
the cost of bid preparation is high;
(b) procurement of particularly high value or
complexity; and
(c) groups of similar items bundled together for
a consolidated purchase.
(7) When prequalification processes are held, the
procuring entity shall–
(a) provide to all bidders responding to the
invitation to prequalify, prequalification
documents which shall provide bidders with
the information required to enable them
prepare and submit their applications for
prequalification;
Qualification
of bidders.
26 27
(b) make available to each applicant the results
of the assessment of qualifications and all
applicants that meet minimum criteria for
prequalification shall be invited to bid.
(8) If prequalification processes are not conducted, postqualification, in which the procuring entity verifies the qualifications
of the bidder selected for award against the criteria stated in the bid
documents, shall be used.
(9) Non-registration with a procurement entity by
suppliers, contractors or consultants shall be a bar to their
participation in public procurement unless the circumstances demand
and it is expressly stated in the particular bidding document.
(1) The procuring entity shall respond within two workingdays to any request by a bidder for clarification of the bidding
documents, or the prequalification documents, submitted to the
procuring entity within the time specified in the bidding documents
or in the prequalification documents.
(2) Responses to requests for clarification, as well as any
modification or any other clarifications of the bidding documents or
of the prequalification documents shall be communicated to all bidders
participating in the procurement processes without delay, so as to
allow bidders an opportunity to take the clarifications or modifications
into account in preparing their submissions and if necessary to allow
bidders to do so, the procuring entity shall extend the deadline for
submission of bids or applications to prequalify.
(1) To the extent possible, any specifications, plans,drawings, designs and requirements or descriptions of goods, works
or services shall be based on the relevant objective technical and
quality characteristic, and performance of the goods, works or services
to be procured; but there shall be no requirement for or reference to
a particular brand, trademark, name, patent, design, type, specific
origin or producer unless there is no other sufficiently precise or
intelligible way of describing the characteristics of the goods, works
or services to be procured and provided that words such as “or
equivalent” are included.
(2) Any descriptions of the technical or quality
characteristics of the goods, works or services to be procured, and
requirements as to testing, packaging, marking, labelling, or conformity
certification, or symbols and terminology, that are irrelevant to the
performance of the goods or create obstacles to participation by
qualified bidders, and thereby limiting competition, shall not be
included or used in the prequalification documents, or bidding
The procuring entity shall set the deadline for submissionof bids, applications for prequalification and expressions of interest
so as to allow sufficient time for their preparation and submission,
with a view to maximising competition, in accordance with the minimum
periods set in sections 39 and 40.
Act and regulations made under it.
(2) A procuring entity may–
(a) reject all bids at any time prior to the
acceptance of a bid;
(b) cancel the procurement processes where–
(i) the procurement need has ceased to
exist or changed significantly;
(ii) insufficient funding is available for the
(iii) there is a significant change in the
required technical details, bidding
conditions, conditions of contract or
other details, such that the recommencement of processes is necessary;
(iv) insufficient, or no responsive bids are
received;
(v) there is evidence of corruption, fraud,
coercion or collusion among bidders;
or
(vi) cancellation is deemed to be in the
interest of national security.
Clarification
and modification of
bidding and
prequalification
Rules for
description of
goods, works
and services.
Deadline for
bids and other
applications.
Cancellation
of processes
for rejection
of all bids.
28 29
(3) Before rejecting all bids or cancelling any procurement
processes, the procurement unit shall prepare a written request for
approval of the cancellation for submission to the procurement
committee, which shall clearly state–
(a) detailed reasons for recommending
cancellation;
(b) the status of the procurement processes,
including in particular, whether bids have
already been opened under bidding methods;
and
(c) whether new procurement processes are
recommended and, if so, the modifications
recommended.
(4) The reason for rejecting all bids, and for cancelling
procurement processes, shall be noted in the record of the procurement
processes, and promptly communicated to the bidders.
(5) A procuring entity shall not be liable to a bidder by
reason only of rejection of all bids or cancellation of procurement
processes under subsection (2).
(6) If a decision to cancel the procurement processes is
taken before the deadline for submission of bids, any bid received
shall be returned unopened to the bidder.
(7) In the event of cancellation or the rejection of all bids
in accordance with subsection (2), the procurement shall not re-bid
to the same specifications and contract conditions unless the
cancellation of the initial proceeding is for budgetary or other reasons
unrelated to the specifications and contract conditions, but if the
procurement is to be repeated, the reasons for the cancellation of the
initial proceeding shall be examined and the technical specification
or contract conditions, or both may be suitably modified prior to re-
The procuring entity shall promptly publish in the Gazetteand any newspaper of wide national circulation notice of each contract
award in which the price of the contract exceeds the threshold set in
the First Schedule, indicating the contract price and the name and
address of the successful bidder.
The procuring entity shall soon after a successfulbidder has been identified, inform the unsuccessful bidder(s) of the
reason for which their respective bids were unsuccessful.
(1) Subject to this Act, documents, notifications,decisions and other communication referred to in this Act to be
submitted by the procuring entity to a bidder or by a bidder to the
procuring entity, shall be in writing
(2) The Authority may authorise procuring entities to use
other forms of communication, including electronic communication,
for publication of invitations to bid, transmission of bidding
documents, submission of bids, conclusion of contracts, and payment
but any such other means of communication shall be such as can
preserve a record of the content of the communication, provide an
adequate level of security, and does not unduly restrict bidders’
access to the procurement processes and is not inconsistent with
this Act or any regulation made under it.
(1) All procuring entities shall undertake procurementplanning, with a view to achieving maximum value for public
expenditures and the other objects of this Act.
(2) The procurement plan to support the procuring
entity’s approved programme and budget shall indicate–
(a) contract packages,
(b) estimated cost of each package,
(c) the procurement method, and
(d) processing steps and times.
(3) A procuring entity shall not divide a procurement order
into parts or lower the value of a procurement order to avoid the
application of the procedures for public procurement prescribed in
this Act.
(4) Where a requirement is divided into lots, which may
result in separate contracts, the selection of procurement method
shall be determined by the estimated total value of all lots.
Public notice
of contract
awards.
Debriefing of
unsuccessful
bidders.
Form of
communication.
planning.
30 31
(5) In accordance with the budget preparation procedures
issued by the Ministry, all procuring entities shall submit their annual
procurement plans for the coming financial year to the Ministry and
the Ministry responsible for local government (for local councils) for
review and approval.
(6) Procuring entities shall, where necessary and on a
quarterly basis, review and update their procurement plans and notify
the Ministry and the Ministry responsible for local government (for
local councils) of any modifications to the approved and updated
plans for publication in accordance with paragraph (i) of subsection
(2) of section 14.
The procuring entity shall be responsible for theadministration of contracts into which it enters, as well as the
monitoring of the performance of such contracts.
(1) Price adjustment shall not be permitted unlessprovided for in the procurement contract to take into account changes
in economic circumstances.
(2) If the procurement contract provides for the possibility
of price adjustment, it shall stipulate the conditions, such as increases
or decreases in the cost of materials, labour, transportation and energy,
in which price adjustment would be permitted; the formulas, and
indices to be referred to in order to determine whether economic
conditions have altered to a significant enough degree to justify a
price adjustment and to identify the amount of increase or decrease;
the frequency with which price adjustments may be implemented;
and procedures to be followed.
(3) The procurement contract may provide that, when
the application of price adjustment leads to a modification exceeding
a stipulated percentage of the initial price or a stipulated percentage
ofthe balance of the contract, the procuring entity may terminate the
(4) Any price variation shall be subject to approval by
the respective procurement committee.
(1) The procuring entity shall preserve all documentationrelating to the procurement processes in accordance with applicable
rules concerning archiving of government documentation, but at a
minimum for a period of six years following the date of final completion
of the procurement contract, or from the date of rejection of all bids or
cancellation of the proceeding, as the case may be.
(2) In addition to the documentation referred to in
subsection (1), the procuring entity shall prepare and maintain a
summary report of the procurement processes, including to the extent
applicable –
(a) a description of the object of the
(b) a list of the participating bidders, their profile
and qualifications, and the qualification
criteria applied;
(c) bid prices;
(d) the bid evaluation criteria;
(e) a summary of the evaluation of bids;
(f) summary of any review processes and
decisions thereon;
(g) requests for clarifications, and responses
thereto;
(h) statement of grounds for cancellation of
procurement processes pursuant to section
25;
(i) statement of grounds for choice of a
procurement method other than open bidding
or request for proposals for services;
(j) statement of grounds for reduction of bid
preparation periods;
(k) information concerning rejection of bids;
(l) such other information as may be required
by the regulations made under this Act.
Contract
administration
responsibility.
Price
adjustment.
Records and
reports of
procurement
processes.
32 33
(3) The portion of the record referred to in paragraphs
(a), (b), (c), (d) and (g) of subsection (2) shall, on request, be made
available to any person after a bid, proposal, offer or quotation has
been accepted or after procurement processes have been terminated
without resulting in a procurement contract.
(4) The portion of the record referred to in paragraphs
(e), (h) and (i) of subsection (2) shall, on request, be made available to
suppliers, contractors or consultants that submitted bids, proposals,
offers or quotations, or applied for pre-qualification, after a bid,
proposal, offer or quotation has been accepted or procurement
processes have been terminated without resulting in a procurement
(5) The procuring entity shall not disclose–
(a) information, if its disclosure will–
(i) be contrary to law,
(ii) impede law enforcement,
(iii) not be in the public interest,
(iv) prejudice legitimate commercial
interests of the parties, or
(v) inhibit fair competition under this Act;
(b) information relating to the examination,
evaluation and comparison of bids,
proposals, offers or quotations, other than
the summary referred to in paragraph (e) of
subsection (2).
(6) Records and documents maintained by procuring
entities on procurement shall be made available for inspection by the
Authority, Anti-Corruption Commission and Auditor-General upon
request; and where donor funds have been utilised for the
procurement, donor officials shall also have access, upon request, to
procurement files for the purpose of audit and review.
(1) Any public officer involved in requisitioning,planning, preparing and conducting procurement processes and
administering the implementation of contracts, shall –
(a) discharge his duties impartially so as to
assure fair competitive access to public
procurement by bidders;
(b) always act in the public interest, and in
accordance with the object and procedures
set out in this Act and regulations made under
it.;
(c) at all times avoid conflicts of interest, and
the appearance of conflicts of interest, in
carrying out his duties and in all his conduct.
(d) not commit or abet corrupt or fraudulent
practices, coercion or collusion, including the
solicitation or acceptance of any
inducements;
(e) keep confidential the information that comes
into his or her possession relating to
procurement processes and to bids, including
bidders’ proprietary information;
(f) not take up a position of authority in any
private concern with which he undertook
procurement activities for a period of three
years after departure from the procuring
entity.
(2) Public officer of a procuring entity, or their close
relatives, shall not participate as bidders in the procurement processes
of the procuring entity.
(3) A public officer shall declare his interest, (direct or
indirect) in writing and in such form as the Authority may prescribe
and excuse himself from any participation in the procurement process
in which there has been a declaration.
(4) A public officer shall excuse himself under subsection
(3) immediately after he becomes aware of the potential conflict; and
the requirement to excuse himself shall extend to the administration
and management of any procurement contract awarded and such
declarations by public officers shall be made to their supervisors and
in the case of a committee member to the Chairman or secretary of the
committee.
Conduct of
public
officials.
34 35
(5) All public officers and other persons involved in
public procurement shall, in accordance with this Act and other
applicable legislation–
(a) provide full cooperation and disclosure to
the Authority, the National Revenue
Authority, Auditor-General, and other
authorities exercising monitoring and
supervisory jurisdiction over public
procurement pursuant to the laws of Sierra
Leone;
(b) not later than thirty days from assuming
responsibility and thirty days after leaving
office, make a declaration of their assets and
liabilities in such form as the Anti-Corruption
Commission may determine; the declaration
shall be updated annually as well as
whenever there is a substantial change in
assets and liabilities.
(6) Public officers who contravene this Act or any
regulation made under it shall be liable to applicable administrative
and civil sanctions as well as to prosecution pursuant to applicable
criminal laws, including the Anti-Corruption Act, 2008.
(1) Bidders and suppliers shall at all times abide bytheir obligations under this Act, the regulations, contracts, and other
instruments applicable to their conduct and activities related to
procurement.
(2) A bidder or a supplier, shall not engage in or abet
corrupt or fraudulent practices, including the offering or giving,
directly or indirectly, of any inducement, the misrepresentation of
facts in order to influence a procurement process or the execution of
a contract, or interference in the ability of competing bidders to
participate in procurement processes.
(3) Bidders shall not engage in any activity, prior to or
after bid submission, designed to deprive the procuring entity of the
benefits of free and open competition, including, but not restricted
to, collusion over bidding for opportunities and price fixing, and
coercive, corrupt or fraudulent practices.
(4) A procuring entity shall reject a bid if the bidder offers,
gives or agrees to give an inducement referred to subsection (2) and
promptly notify the rejection to the bidder concerned, the Authority,
and to the relevant law enforcement authorities.
(5) The procuring entity shall not award a contract to a
bidder who is responsible for preparing the specifications or bidding
documents for the contract or supervising the execution of a contract,
or to any affiliate of such a bidder; but this subsection shall not
apply to the various firms (consultants, contractors or suppliers)
which together are performing the supplier’s obligations under a
turnkey or design and build contract.
(6) Any bidder or supplier who is engaged in any
fraudulent, corrupt or coercive practice in connection with public
procurement commits an offence and on conviction be liable to a fine
not less than 10 % of the value of the contract or to imprisonment for
a term not exceeding five years or to both such fine and imprisonment.
(1) The Authority may exclude a bidder or a supplierfrom participation in public procurement for a minimum period of one
year and a maximum period of six years after –
(a) consultation with the affected procuring
entity to consider all the facts of the case;
(b) reasonable notice to the bidder or supplier
involved of the cause of the proposed
actions; and
(c) reasonable opportunity for the bidder or
supplier to respond to the proposed action.
(2) A potential bidder or supplier shall not be debarred
from participation in procurement except on the following grounds–
(a) provision of false information supplied in the
process of submitting a bid;
(b) collusion between the bidder and another
bidder or a bidder and a public officer
concerning the formulation of any part of the
bidding documents;
Conduct of
bidders and
suppliers.
36 37
Debarment of
bidders and
suppliers.
(c) connivance to interfere with the participation
of competing bidders;
(d) misconduct relating to the submission of bids,
including corruption, collusion, price fixing,
a pattern of under-pricing of bids, breach of
confidentiality, and any other misconduct
referred to in section 34;
(e) non-performance of contractual obligations
under a contract deemed serious enough to
warrant debarment, provided that the nonperformance was not due to circumstances
beyond the control of the supplier;
(f) conviction of a criminal offence relating to
obtaining or attempting to obtain a contract
or subcontract;
(g) non-settlement of tax obligations after
assessment by the National Revenue
Authority or the evasion of tax by any means;
or
(h) conviction of a crime related to business
or professional activities.
(3) The Ministry shall effect debarment of a bidder or a
supplier excluded by the Authority under subsection (1), by not
releasing funds to pay on any contract entered into between a
procuring entity and the debarred bidder or supplier.
(1) A procuring entity may grant a margin of preferencefor the benefit of bids for work by domestic contractors or for the
benefit of bids for domestically produced goods or for the benefit of
domestic suppliers of services;
(2) The margin of preference shall be calculated in
accordance with the regulations and reflected in the record of the
procurement processes;
(3) The margin of preference shall be authorised by the
Authority and shall be subject to approval by the Authority.
PART V–METHODS OF PROCUREMENT
(1) Public procurement shall be undertaken by means ofadvertised open bid processes, to which equal access shall be
provided to all eligible and qualified bidders without discrimination,
subject only to the exceptions provided in sections 38, 39, 40 and 41.
(2) Procurement shall not be divied artificially with the
intention of avoiding the monetary thresholds established under to
this Act or regulations made under it.
(3) If the procuring entity uses a method of procurement
other than advertised open bidding or, in the case of procurement of
consultant services, a method other than request for proposals, it
shall note in the record of the procurement processes the grounds
for the choice of the procurement method.
(4) When the participation of the procurement end-user
or beneficiary community may result in enhancing the economy,
quality or sustainability of the service to be procured, or the very
objective of the project is to create employment and involvement of
the beneficiary community, such end-user or community may
participate in the delivery of services under procedures to be defined
in the regulations.
(5) In the cases referred to in subsection (4), procurement
may be carried out by force account, in which the procurement is
carried out with self-supervision, utilising the procuring entity’s own
personnel and equipment or those of another government institution.
(6) The cases in which force account may be utilised
include, separately or in combination with any activity–
(a) that, in view of its size, nature, location or
scattered locations (with no local suppliers
available), financing or high demobilization
costs for outside suppliers, does not attract
bidders, at least not at a reasonable price;
38 39
Margin of
preference.
Choice of
procurement
method.
(b) that cannot be calculated, or determined in
detail in advance or both, such that, if it were
carried out by a supplier, contractor, or
consultant, it would have to bear a large risk;
(c) where the risk of unavoidable work
interruptions is better borne by the procuring
entity than by a supplier or contractor;
(d) where it has been demonstrated that force
account is the only practical method for
constructing and maintaining works under
special circumstances;
(e) for a pilot project of a particular nature for
development of a technology or work method
or both that cannot yet be carried out by a
supplier; and
(f) for works that must be carried out without
disrupting existing operations by the
procuring entity’s crew familiar with those
operations.
(7) Where any procurement of goods, sub-contracted
works or services is required to supplement the force account activity,
that procurement shall be carried out in accordance with the
appropriate provisions of this Act.
(1) The open bid processes may include aprequalification stage or apply a post qualification procedure prior to
the award of contract.
(2) The open bid may be carried out in a single stage or in
two stages, but the use of the two-stage method shall be used in the
circumstances specified in subsection (3).
(3) An open bid may be held in two stages in the following
cases–
(a) when it is not feasible to define fully the
technical or contractual aspects of the
procurement to elicit competitive bids; and
(b) when, because of the complex nature of the
goods, works or services to be procured, the
procuring entity wishes to consider various
technical or contractual solutions, and to
discuss with bidders about the relative merits
of those variants before deciding on the final
technical or contractual specifications.
(1) In procurement processes in which the procuringentity decides that only domestic suppliers or contractors are likely
to be interested in submitting bids, the procuring entity may employ
national competitive bidding procedures.
(2) The procuring entity shall not be required to employ
national competitive bidding procedures if the estimated contract
amount is lower than the value threshold specified in the First
Schedule.
(3) The procuring entity may stipulate in the bidding
documents that bidders must quote only in the local currency and
payments shall be made wholly in the local currency.
(4) At least four weeks shall be allowed for submission
of tenders in order to allow sufficient time for the invitation to reach
candidates and to enable them to prepare and submit the bids as
provided in section 24.
(1) The procuring entity shall employ internationalcompetitive bidding procedures when the estimated contract amount
is higher than the value threshold specified in the First Schedule.
(2) International competitive bidding may be used
whenever open competitive bidding is used and effective competition
cannot be obtained unless foreign firms are invited to bid or where
the goods, works or services are not available under competitive
price and other conditions from three or more suppliers in Sierra
Leone.
40 41
Open
competitive
National
competitive
International
competitive
bidding..
(3) International competitive bidding shall be in
accordance with the appropriate procedures prescribed in this Act
together with the following;–
(a) the invitation to bid and bidding documents
shall be in English;
(b) the invitation to bid shall also be published
in a newspaper of wide international
circulation, in a relevant trade publication or
technical or professional journal of wide
international circulation.;
(c) at least six weeks shall be allowed for
submission of bids in order to allow sufficient
time for the invitation to reach candidates
and to enable them to prepare and submit the
tenders as provided in section 23;
(d) technical specifications shall, to the extent
compatible with national requirements, be
based on international standards or
standards widely used in international trade
and in particular shall conform to the
provisions of section 23;
(e) bidders shall be permitted to express their
bids, as well as any security documents to
be presented by them, in their respective
domestic currencies, or in a currency widely
used in international trade and stated in the
bidding documents;
(f) general and special conditions of contract
shall be of a kind generally used in
international trade.
(1) Subject to approval by the Procurement Committee,restricted bidding may be held in the following cases:–
(a) when the goods, works or services are only
available from a limited number of bidders;
(b) when the time and cost of considering a large
number of bids is disproportionate to the
estimated value of the procurement.
(1) When restricted bidding is employed on the groundsreferred to in paragraph (a) of section 41, all known suppliers
capable of supplying the goods, works or services shall be invited to
bid.
(2) When restricted bidding is employed on the grounds
referred to in paragraph (b) of section 41, the procuring entity shall
solicit bids from a minimum number of five bidders, if possible.
(3) The procedures for bidding processes, as set forth in
Part V, shall apply to restricted bidding, except to the extent that they
are modified by this section.
Request for proposals for services is the method to beused for the procurement of consultant services, subject only to the
exceptions specified in section 46.
The request for quotations method may be used for theprocurement of goods and works–
(a) where the procurement is for readily available
commercially standard goods, not specially
manufactured to the particular specifications
of the procuring entity and the estimated
value does not exceed the amount set in the
First Schedule;
(b) when the estimated value of the procurement
of small works, does not exceed the amount
set in the First Schedule;
(c) when the estimated value of the procurement
of services does not exceed the amount set
in the First Schedule.
(1) Quotations shall be requested in writing from as manybidders as practicable, but from at least three bidders.
(2) The request shall contain a clear statement of the
requirements of the procuring entity as to quality, quantity, terms
and time of delivery, as well as any other special requirements.
42 43
Restricted
Procedures
for restricted
Request for
proposals.
Request for
quotations.
Basic procedures for
request
for quotation.
(3) Bidders shall be given adequate time to prepare and
submit their quotations, but each bidder shall be permitted one
quotation, which may not be altered or negotiated.
(4) A purchase order shall be placed with the bidder that
provided the lowest-priced quotation meeting the delivery and other
requirements of the procuring entity.
(1) Public procurement by means of the sole-sourceprocurement method shall be permitted only in the following
circumstances-
(a) when only one supplier has the exclusive right
to realise manufacture of the goods, carry
out the works, or perform the services to be
procured and no suitable alternative is
available;
(b) for additional deliveries of goods by the
original supplier which are intended either as
part replacement for existing goods, services
or installations, or as the extension of existing
goods, services or installations where a
change of supplier would compel the
procuring entity to procure equipment or
services not meeting requirements of interchangeability with already existing equipment
or services;
(c) when additional works, which were not
included in the initial contract have, through
unforeseeable circumstances, become
necessary and the separation of the
additional works or services from the initial
contract would be difficult for technical or
economic reasons;
(d) in cases of extreme urgency, provided the
circumstances which gave rise to the urgency
were neither foreseeable by the procuring
entity nor the result of dilatory conduct on
its part;
(e) when the services require that a particular
consultant be selected due to his unique
qualifications, or when it is indispensable to
continue with the same consultant.
(2) Use of sole-source procurement on the grounds
referred to in paragraphs of section (1) shall be subject to prior
approval by the Procurement Committee.
(1) When the procuring entity engages in sole- sourceprocurement on the grounds referred to in subsection (1), it shall
prepare a written description of its needs and any special
requirements as to quality, quantity, terms and time of delivery; and
shall request submission of a bid or proposal in writing or both and
shall be free to negotiate with the sole bidder.
(2) Publication in the Gazette, a newspaper of national
circulation and, when feasible on the internet, of a notice of the holding
of sole-source procurement processes is required when the estimated
value of the procurement exceeds the threshold set in First Schedule.
PART VI–BIDDING PROCEDURES
(1) An invitation to bid, or an invitation to prequalify,shall be published in the Gazette, national print media of wide
circulation and electronic media.
(2) Every invitation to bid or to apply for prequalification
published under subsection (1), shall run for the period of time
prescribed in subsection (4) of section 39 and paragraph (c) of
subsection (3) of section 40.
(3) A procuring entity may limit participation on the basis
of nationality in accordance with the regulations and shall include in
the record of the procurement proceedings a statement of the grounds
and circumstances on which it relied.
(4) Tenders shall be formulated and submitted in English
and except where the Authority otherwise determines or the specific
instruction in a bidding package or a Tender Notice so requires, English
shall be the official language of all communications.
44 45
Sole-source. Basic
procedures for
sole-source
procurement.
Invitation to
bid.
(5) Supporting documents and printed literature furnished
by a bidder may be in another language if they are accompanied by
an accurate translation of the relevant passages in English.
(6) Translations may be used to interpret a bid.
(7) In an international bid, in which the participation of
foreign bidders is invited, an invitation to bid or an invitation to
prequalify in accordance with section 21 shall be published in English
and where–
(a) the estimated value of the procurement
exceeds the thresholds set in the First
Schedule; or
(b) there is no response to a national bidding
proceeding,
the bidding and contract documents shall also be made in English.
(8) The invitation to bid or to prequalify, as the case may
be, shall include information on–
(a) the identity and address of the procuring
entity;
(b) the nature and time-frame of the procurement,
including the place of delivery of goods or
services, and the location of any works;
(c) the manner of obtaining and the price of the
bidding documents, or, if applicable, the
prequalification documents;
(d) the place and deadline for submission of bids,
or of applications to prequalify;
(e) such other matters as the Authority may by
statutory instrument prescribe.
(1) A procuring entity shall use the appropriate standardbidding documents specified in the second Schedule.
Provided that in exceptional circumstances, the Authority may, on an
application by a procuring entity, approve in writing, the usage of
other formats or variations to the standard bidding documents.
(2) A procuring entity shall provide, in an expeditious
and non-discriminatory manner, the bidding documents to all potential
bidders that respond to the invitation to bid or, in the case of
prequalification, to all bidders that have been prequalified, and the
price that may be charged for the bidding documents shall reflect
only the cost of printing and distributing the documents.
(3) The bidding documents shall inform bidders of–
(a) the nature and time frame of the procurement,
including, but not limited to the technical
specifications or drawings as the case may
be, terms of reference, the contractual terms
of the procurement, and the manner of entry
into force of the contract;
(b) bidder qualification requirements if a
prequalification procedure was not followed;
(c) information as to site visits and pre-bid
conferences;
(d) instructions for preparation and submission
of bids, including the deadline for submission
of bids, time and place of bid opening;
(e) components to be reflected in the price, the
currency or currencies in which the bid price
may be stated, and the currency and related
exchange rate to be used for comparison of
bids;
(f) the criteria and methodology for evaluation
of bids and the selection of the successful
bidder, which shall all be quantified in
monetary terms or expressed in the form of
pass or fail requirements, if possible, or, where
not possible, by relative weights and when
considering evaluation criteria, the procuring
entity shall consider only the following -
(i) the bid price, subject to any margin of
preference applied pursuant to section
36;
46 47
Bidding
(ii) the cost of operating, maintaining and
repairing the goods or works, the time
for delivery of the goods, completion of
works or provision of the services, the
functional characteristics of the goods
or works, the terms of payment and of
guarantees in respect of the goods,
works or services;
(iii) the effect that acceptance of a bid would
have on the environment, the extent of
local content, including local
manufacture, labour and materials, in
goods, works or services being offered
by bidders, the transfer of technology
and the development of managerial,
scientific and operational skills;
(g) the preference, if any, for domestic goods and
contractors as the Authority may by statutory
instrument prescribe.
(h) any grouping of goods, works or services
into lots and packages and the manner of
evaluation of the lots and packages;
(i) whether alternatives to the technical or
contractual specifications would be
considered and, if so, how those alternatives
would be evaluated;
(j) if suppliers are permitted to submit bids for
only a portion of the goods, works or services
to be procured, a description of the portion
or portions for which bids may be submitted;
(k) the required validity period of bids;
(l) the amount and acceptable forms of any
required bid, performance or other security;
(m) the conditions of contract which will be
entered into with the successful bidder;
(n) notice of conflict-of-interest restrictions and
anti-fraud and corruption rules;
(o) the manner in which bidders may obtain
review of actions, omissions and decisions
of the procuring entity; and,
(p) such other matters as the Authority may by
statutory instrument prescribe.
(1) Subject to subsection (2) of section 28, a bid shall notbe accepted unless submitted in writing, duly signed, in a sealed
envelope within the deadline for submission of bids and any bid
received after the deadline for submission of bids shall be returned
unopened.
(2) Invitation for bidding and prequalification documents
shall permit submission of applications to bid or prequalify by hand
or mail or by courier at the option of the bidder.
(3) The Authority may by statutory instrument prescribe–
(a) other methods of submission of bids, such
as by electronic mail;
(b) rules for the protection of the confidentiality
and security of bids, including the
prevention of the opening and reading of
bids by anyone until the time set in
accordance with paragraph (d) of subsection
(3) of section 49.
(4) Bids shall remain valid for the period of time indicated
in the bidding documents, but modification or withdrawal of a bid
during the bid validity period is subject to forfeiture of the bid security.
(5) The validity period of a bid may be deemed extended
only on the basis of the agreement of the bidder concerned and
bidder that agrees to an extension of the validity period of its bid
shall also obtain a corresponding extension of the bid security, if
such a security was required.
(1) The bidding documents may require every bidder tosubmit a bid security, which shall be on such terms and conditions
as the Authority may by statutory instrument prescribe.
(2) Forfeiture of a bid security may be imposed only in
the event of–
48 49
Submission of
bids.
Bid security.
(a) a modification or withdrawal of a bid after the
deadline for submission of bids and during
its period of validity;
(b) refusal by a bidder to accept a correction of
an arithmetical error appearing on the face of
the bid;
(c) failure by the successful bidder to sign a
contract in accordance with the terms set forth
in the bidding documents; or
(d) failure by the successful bidder to provide a
security for the performance of the contract
if required to do so by the bidding documents.
(1) Bids shall be opened at the time and place indicatedin the bidding documents, and the time of bid opening shall coincide
with the deadline for submission of bids, or follow immediately
thereafter, allowing a minimum time interval for logistical reasons.
(2) Bidders or their representatives may attend the bid
opening, where the name of the bidder, the total amount of each bid,
any discounts or alternatives offered, and the presence or absence
of any bid security, if required, and essential supporting documents
shall be read out loud and recorded, and a copy of the record shall be
made available to any bidder on request; and any documents with
financial implications must be signed by the Chairman and two other
members of the bid opening committee.
(3) No decision regarding the disqualification or rejection
of any bid shall be taken or announced in the bid opening session.
(4) Following opening of the bids, and until the preliminary
decision on award has been notified to the successful bidder, no
bidder shall make any unsolicited communication to the procuring
entity or try in any way to influence the procuring entity’s examination
and evaluation of the bids.
(1) Following the opening of bids, the procuring entityshall first examine the bids in order to determine whether the bids are
complete, signed, whether required documents to establish legal
validity and required bid security have been furnished and whether
bids are substantially responsive to the technical specification and
contract conditions set forth in the bidding documents.
(2) Bids which are not complete, not signed, not
accompanied by a bid security in the prescribed form, if one is
required, or not accompanied by essential supporting documents
such as business registration certificates, business licences and tax
receipts, or are substantially non-responsive to the technical
specifications or contract conditions or other critical requirements
in the bidding documents, shall be rejected and excluded from further
evaluation and comparison.
(3) The Authority may by statutory instrument prescribe–
(a) other methods of submission of bids, such
as by electronic mail;
(b) protecting the confidentiality and security
of bids, including the prevention of the
opening and reading of bids by anyone until
the time set in accordance with paragraph
(d) of subsection (3) of section 49.
(4) Bids not excluded from consideration under
subsections (2) and (3), shall be evaluated taking into account those
factors explicitly stated in the bidding document.
(5) The procuring entity may seek clarification from any
bidder to facilitate evaluation but shall neither ask nor permit any
bidder to change the price or any other aspect of the bid and if a
bidder amends its bid in any manner, that bid will be rejected and its
bid security forfeited.
(6) Where there is an arithmetical error, the error shall be
rectified and the bidder notified but if the bidder refuses to accept
such correction, its bid shall be rejected and the bid security forfeited.
(7) Where there is a discrepancy between figures and
words, the amount in words shall prevail unless the discrepancy is
due to misplacement of decimal point, in which case the mistake
shall be rectified and the bidder notified.
50 51
Bid opening.
Examination
evaluation
and comparison of
bids.
(8) In carrying out the evaluation, if there are minor
deviations in any bid which did not merit rejection at the earlier stage,
such minor variation shall be costed, if possible, and the evaluated
cost of the bid shall then be compared to those of other bids to
determine the lowest evaluated bid.
(9) Where the process included a prequalification, the
qualifications of the lowest evaluated bidder shall be verified again
to take account of any change since the original prequalification.
(10) Where there was no prequalification, the
qualifications of the lowest evaluated substantially responsive bidder
shall be checked against the criteria specified in the bidding
documents; if that bid fails, the same check shall be applied to the
next ranked bid.
(11) The procuring entity shall prepare an evaluation report
detailing the examination and evaluation of bids and identifying the
recommendation for award of contract in accordance with the
evaluation criteria specified in the bidding document.
Information relating to the examination, clarification,evaluation and comparison of bids shall not be disclosed to
suppliers or contractors or to any other person not involved officially
in the examination, evaluation or comparison of bids or in the
decision on which bid should be accepted, except as provided in
subsections (3) and (4) of section 32.
(1) No negotiation shall take place between theprocuring entity and the supplier or contractor with respect to a bid
submitted by the supplier or contractor.
(2) Where the lowest evaluated responsive bid exceeds
the budget for the contract by a substantial margin, the procuring
entity shall investigate the causes for the excessive cost and may
request new bids.
(1) The contract shall be awarded to the bidder havingsubmitted the lowest evaluated and substantially responsive bid
which meets only those evaluation criteria as specified in the bidding
(2) Prior to the expiry of the period of bid validity, the
procuring entity shall notify the successful bidder of the proposed
award, which shall specify the time within which the contract must be
signed, subject to any intervening complaints filed in accordance
with Part VI.
(3) Notice of award shall be given to other bidders at the
same time the successful bidder is notified, specifying the name and
address of the proposed bidder and the price of the contract, but the
contract shall not be signed until at least 14 calendar days have
passed following the giving of that notice.
(4) Where a bidder whose bid has been accepted fails to
sign a written contract, when required to do so, or fails to provide
any required security for the performance of the contract within the
prescribed time limit, the procuring entity shall accept the next ranked
bidder from among the remaining bids that are in force, but in selecting
the next ranked bidder, the procuring entity shall comply with
provisions of section 52 as appropriate.
(5) Any person who signs or enters into a procurement
contract on behalf of a procuring entity where there is a pending
complaint and in contravention of this subsection commits an offence
and shall be liable on conviction to a fine not exceeding 10 % of the
value of the contract or to imprisonment for a term not exceeding five
years or to both such fine and imprisonment.
(1) Where the bidding documents require the supplier orcontractor whose bid has been accepted to sign a written procurement
contract conforming to the bid, the procuring entity and the supplier
shall sign the procurement contract within 30 days after the notice
referred to in subsection (2) of section 56 has been dispatched to the
supplier or contractor.
(2) Where a written procurement contract is required to
be signed, the procurement contract shall enter into force when the
contract is signed by the supplier or contractor and by the procuring
entity.
52 53
Acceptance
of bid and
signature of
Nondisclosure of
bid evaluation details.
Prohibition of
negotia-tion.
Award of
(3) Except as provided in subsection (2) of section 56, a
procurement contract in accordance with the terms and conditions of
the accepted bid shall enter into force when the notice is dispatched
to the supplier or contractor that submitted the bid while the bid is in
force.
(4) Contracts shall be signed by the head of a procuring
entity, but he may delegate signature of small contracts to the head
of procurement unit or other senior official of the entity.
(5) Any contracts entered into between a procuring entity
and a successful bidder shall be valid only if it contains an express
provision allowing cancellation of the contract by the Panel if
the panel finds a contravention of any provision of this Act or any
regulation, document or process relating to the procurement.
(1) Where a procurement is to be done by a two- stagebidding, the bidding documents shall, in the first stage, require bidders
to submit initial bids without a bid price, and may solicit initial
proposals relating to the technical, quality or other characteristics of
the goods, works or services, as well as to contractual terms and
conditions of the proposed contract, and, where relevant, the
professional and technical competence and qualifications of the
bidders.
(2) The procuring entity may engage in discussion with
any or all bidders whose proposals satisfy the conditions set forth in
the bidding documents with a view to understanding the proposals
or to indicate changes required to make them acceptable and to seek
the bidder’s willingness to make such changes and the minutes of
these discussions shall form part of the procurement records.
(3) At the end of the first stage, the procuring entity may–
(a) reject those bids which do not, and cannot
be changed to meet the basic requirements,
minimum performance, or required
completion time or have any other weakness
which makes the bid substantially non
responsive;
(b) modify the technical specifications,
evaluation criteria, and contract conditions,
while seeking to maximise competition and
articulate appropriate evaluation methodology.
(4) In the second stage, the procuring entity shall invite
bidders whose bids have not been rejected to submit final bids with
prices responsive to the revised bidding documents.
(5) A bidder, not wishing to submit a final bid, may
withdraw from the bidding processes without forfeiting any bid
security that the bidder may have been required to provide, and the
final bids shall be evaluated and compared in accordance with the
criteria and methodology included in the revised bidding documents.
(6) The procedures for bidding specified in section 57
shall apply to two-stage bidding processes, except to the extent they
are modified by this section.
(1) For the purposes of procuring the services of aconsultant, the procuring entity shall prepare a shortlist of three to
six consulting firms, to the greatest extent feasible, comprising
consultants of the same category, and similar capacity and business
objectives, to which it shall provide the request for proposals for
services; and the short-list shall be established from among those
who have capacity to perform the required services, as demonstrated
in their submissions.
(2) When the estimated value of the procurement exceeds
the threshold set out in the First Schedule, in order to establish the
shortlist, the procuring entity shall seek expressions of interest by
publishing a notice in the Gazette, in a national print media of wide
circulation, and whenever feasible, on the internet, and where
appropriate, the notice may also be published in a relevant trade
publication or technical or professional journal.
54 55
Two-stage
Request for
consultant’s
services.
(3) For assignments of a value lower than the threshold
set out in the First Schedule, the shortlist may be established from
market knowledge, or other sources of information but in the case of
assignments which have an estimated value above that threshold, or
are particularly complex, an advertisement shall also be utilised.
(4) The request for proposals shall provide short listed
bidders with the information necessary to enable them to participate
in the procurement processes and to submit proposals that are
responsive to the needs of the procuring entity including, in particular:
(a) the name and address of the procuring entity;
(b) the nature, time frame and location of the
services to be provided, terms of reference,
required tasks and outputs;
(c) the criteria to be used in evaluating and
comparing proposals, and their relative
weight as compared to price;
(d) the contractual terms of the procurement, and
the manner of entry into force of the contract;
(e) instructions for preparation and submission
of proposals, and the place and deadline for
submission of proposals;
(f) the final selection procedures to be applied;
(g) notice of conflict-of-interest restrictions and
anti-fraud and corruption rules, including the
grounds for potential debarment from future
participation in procurement of goods,
services or works that may result from the
assignment under consideration; and
(h) such other matters as may be prescribed in
the regulations and standard documents
issued by the Authority.
(6) The price of a proposal shall be considered by the
procuring entity only after completion of the technical evaluation.
(1) The selection of the successful proposal shall bebased either–
(a) on the technical quality of the proposal, the
consultant’s relevant experience and the
expertise of its staff, and the proposed work
methodology, as well as the price of the
proposal;
(b) on the quality of the technical proposal
submitted within a predetermined fixed
budget; or
(c) on the basis of the best financial proposal
submitted by the candidates, having
obtained an acceptable technical score predisclosed in the request for proposals.
(2) Detailed procedures shall be set out in the regulations.
When the services are of an exceptionally complex natureof a considerable impact on future projects or national economy or
when they may lead to the submission of proposals which are difficult
to compare, the consultant may, subject to the approval of the
procurement committee, be selected exclusively on the basis of the
technical quality of his proposal.
(1) The contract may be negotiated with the selectedconsultant but negotiations may not be simultaneously held with
several consultants.
56 57
Selection or
based on
quality.
Contract
award.
Selection
based on
quality and
cost.
(2) The procuring entity shall notify its proposed award
to all short-listed consultants at the same time it notifies the selected
consultant, but where the value of the contract exceeds the levels set
out in the regulations, the contract shall not be signed until at least
14 calendar days have passed following the giving of that notice.
(3) The selected consultant shall not be permitted to
substitute key staff, unless both parties agree that undue delay in
the selection process makes such changes unavoidable or that such
changes are critical to meet the objectives of the assignment.
(4) The key staff proposed for substitution shall have
qualifications equal to or better than the key staff initially proposed.
PART VII –COMPLAINTS PROCEDURE
(1) A potential or actual bidder that claims to havesuffered, or that is likely to suffer, loss or injury due to a breach of a
duty imposed on the procuring entity by this Act, the regulations
and the bidding document, may seek review in accordance with this
Part, at any stage of the procurement processes.
(2) An application for review under subsection (1), shall
not be entertained unless it identifies the specific act of omission or
commission alleged to contravene this Act or the regulations and the
bidding document.
(3) Where an application for review concerns alleged
improprieties in the solicitation of applications to prequalify, or to
solicitation of bids, which are apparent prior to bid opening, such
applications shall be entertained only if submitted prior to bid opening.
(1) Prior to the entry into force of a contract, applicationfor review shall be made, in the first instance, in writing, to the head
of the procuring entity.
(2) The head of the procuring entity shall not entertain
an application for review unless it was submitted within 14 calendar
days, or when the bidder submitting it became aware of the
circumstances giving rise to the complaint or of when that bidder
should have become aware of those circumstances, whichever is
earlier.
(3) Unless the complaint is resolved by mutual agreement,
the head of the procuring entity shall suspend the procurement
processes and shall, within five working days after submission of the
complaint, issue a written decision, stating the reasons, and, if the
complaint is upheld, indicating the corrective measures to be taken.
(4) If the Head of the procuring entity does not issue a
decision within the time stated in subsection (3), or if the complainant
is not satisfied with the decision of the head of the procuring entity,
the complainant is entitled to submit a complaint to the Panel pursuant
to section 65.
(5) Complaints under subsection (4) shall not be heard
unless submitted to the Panel within ten working days from the elapse
of the time stated in subsection (3) or from the date on which the
entity’s decision was communicated to the complainant.
(1) Subject to subsection (4), an application for reviewmay be brought before the Panel in the following circumstances–
(a) in the form of an appeal by the complaining
bidder against a decision by the head of the
procuring entity, provided that the appeal is
submitted within ten working days of the
date of the decision;
(b) where the head of a procuring entity fails to
render a decision within the required time
frame, provided that the application for review
is filed within ten working days of the expiry
of the time for the decision by the head of the
procuring entity referred to in subsection (3)
of section 64;
58 59
Review by
independent
procurement
review panel.
Right to
review.
Review by
head of
procuring
entity.
(c) in the case where the contract has already
entered into force, any application for review
submitted in the first instance to the Panel
shall not be entertained unless it is submitted
to the Panel within ten working days of when
the bidder submitting it became aware of the
circumstances giving rise to the complaint or
of when that bidder should have become
aware of those circumstances, whichever is
earlier.
(d) in the form of an appeal by the complaining
bidder against a decision by the Authority
pursuant to a debarment process.
(2) In order for an application for review to be considered
by the Panel, the application shall be accompanied by both an
administrative fee and a complaint fee as specified in the regulations.
(3) The Panel shall make a decision under this section
within ten working days after receiving the complaint.
(4) A complaint may be dismissed for–
(a) failure to comply with any of the requirements
of this Part;
(b) setting forth only allegations that do not state
a valid basis for a complaint, or that do not
set forth a detailed legal and factual
statement;
(c) having been filed in an untimely manner,
either at the initial level of review by the
procuring entity, or with respect to deadlines
for filing of a complaint with the Panel;
(d) reasons relating to contract implementation
or administration rather than contract award;
(e) challenging an affirmative determination of
qualifications of a competing bidder.
(5) Unless a complaint is dismissed, the remedies that
may be ordered by the Panel include–
(a) prohibiting the procuring entity from acting
or deciding in an unauthorized manner or
from following incorrect procedure;
(b) annulling in whole or in part any
unauthorised act or decision of a procuring
entity, including contract award or any
decision or act bringing the contract into
force;
(c) reversing a decision by the procuring entity
or substituting its own decision for such
a decision;
(d) award of costs incurred in participating in
the bidding process where the results were
not in accordance with this Act or any
regulation made under it.
(6) Where a timely submission of a complaint is made in
accordance with deadlines set in this section the procurement
processes shall be suspended until a decision on the complaint is
issued by the Panel.
60 61
(7) The suspension under subsection (6) shall not apply
if the procuring entity certifies to the Panel that urgent public interest
considerations, such as natural disasters, medical emergencies, civil
strife and outbreak of war, require the procurement to proceed.
(8) The certification, under subsection (7) shall state the
grounds for the finding that urgent considerations exist and which
shall be made a part of the record of the procurement processes, and
shall be conclusive with respect to all levels of review, except judicial
review.
(9) Where the Panel has found that a criminal act may
have been committed, it shall forward its decision and
recommendations to the competent authority for possible criminal
investigations or prosecution
PART VIII – DISPOSAL OF STORES AND EQUIPMENT
Assets Commission Act, 2000 the head of a procuring entity shall
convene a Board of Survey comprising representatives of
departments with unserviceable, obsolete or surplus stores, plant,
equipment and vehicles which shall report on the items and, subject
to a technical report on them, recommend the best method of disposal
after the officer in charge has completed a Board of Survey form.
(2) The Board of Survey’s recommendations shall be
approved by the head of the procuring entity and the items shall be
disposed of following disposal procedures specified in section 67.
(3) Where items become unserviceable for reasons other
than fair wear and tear, such as through accident or expiry, a set
procedure established by the Board for handling losses shall be
followed before the items are boarded and disposed of.
(a) transfer to government departments or other
public entities, with or without financial
adjustment;
(b) sale by public bid to the highest bidder,
subject to reserve price;
(c) sale by public auction, subject to reserve
price; or
(d) destruction, dumping, or burying as
appropriate.
PART IX – MISCELLANEOUS
(1) The Authority may by statutory instrument, makeregulations for giving effect to this Act.
(2) Without prejudice to subsection (1), regulations made
under this Act may provide for–
(a) standard bidding documents, request for
proposals and other forms to be used on a
mandatory basis by procuring entities;
(b) the preparation and submission of bids;
(c) the manner of publication of the notice of
procurement contract awards;
(d) the margin of preference in the evaluation of
bids;
62 63
Disposal
procedures.
Regulations.
Authority to
dispose.
(e) the preparation and submission of
applications to pre-qualify for a bids
(f) detailed procedures for selection of
consultants using methods other than those
specified in sections 59 to 62; .
(g) procurement processes on the basis of
nationality;
(h) the procurement process where one entity or
a specially appointed agent is to procure items
on behalf of another entity;
(i) the amendment of the thresholds for
procurement methods and award of contracts
under the First Schedule;
(j) sample forms of the procurement plans;
(k) print and electronic media acceptable for
publication in compliance with this Act; and
(l) on any other matter connected under this Act
with public procurement.
(2) Notwithstanding the repeal of the Public Procurement
Act, 2004 under subsection (1), any order, rules, notices or regulation
made under the repealed Act and in force immediately before the
coming into force of this Act shall, unless revoked, continue in force.
THRESHOLDS SECTIONS 40, 44, 48 (2), 59, 68, (2) (11)
1. Contract awards shall be published when the estimated value of the contract
is above :
(a) In the case of contracts for the procurement of goods, Le 300.00
(b) In the case of contracts for the procurement of works, Le 600.00
(c) In the case of contracts for the procurement of services, Le 300.00
2. Request for Quotation shall be used when the estimated value of the
procurement is below:
(a) In the case of contracts for the procurement of goods, Le 60.00
(b) In the case of contracts for the procurement of works, Le 150.00
(c) In the case of contracts for the procurement of services, Le 60.00
3. National Competitive Bidding (N.C.B.)shall be used when the estimated
value of the procurement is below:
(a) In the case of contracts for the procurement of goods, Le 600.00
64 65
Repeal of Act
No. 14 of
20 04
(b) In the case of contracts for the procurement of works, Le 900.00
(c) In the case of contracts for the procurement of services, Le 600.00
4. International Competitive Bidding (I.C.B.) shall be held when the estimated
value of the procurement exceeds:
(a) In the case of contracts for the procurement of goods, Le 600.00
(b) In the case of contracts for the procurement of works, Le 900.00
(c) In the case of contracts for the procurement of services, Le 600.00
5. Expression of Interest for Selection of Consultants
The solicitation of expressions of interest is required when the estimated value of
the consultants’ services is above Le 600.00 million.
6. Approval of Contract Awards
Type of contract Contract Value (Le) Authority approving
(Threshold in SLL million) proposed contract award
1. Goods Less than 15 Head of Procurement Unit or
Department
15-60 Head of Procuring Entity
Above 60 Procurement Committee
2. Works/Tech- Less than 30 Head of Procurement Unit
nical Services or Department
30-100 Head of Procuring Entity
Above 100 Procurement Committee
3. Consulting Less than 6 Head of Procurement Unit or
Services Department
6-30 Head of Procuring Entity
Above 30 Procurement Committee
66 67
SECOND SCHEDULE - STANDARD BIDDING DOCUMENTS
SECTION 49
1. GOODS
(a) RFQ
(b) NCB
(c) ICB
(d) Health goods
(e) Information Technology (IT) Goods
2. WORKS
(a) RFQ
(b) NCB
(c) ICB
3. SERVICES
(a) Request for Proposals for small contracts (less than Le 300.00 million)
(b) Request for Proposals for large contracts (above Le300.000 million).
68 69
PRINTED AND PUBLISHED BY THE GOVERNMENT PRINTING DEPARTMENT, SIERRA LEONE.
GAZETTE NO. 10 OF 25TH FEBRUARY, 2016.
Passed in Parliament this 3rd day of November, in the year of our Lord two
thousand and Fifteen.
IBRAHIM S. SESAY,
Clerk of Parliament.
THIS PRINTED IMPRESSION has been carefully compared by me with the Bill
which has passed Parliament and found by me to be a true and correct printed copy
of the said Bill.
IBRAHIM S. SESAY,
Clerk of Parliament.
Check the current official version before relying on this text. MiLAWYER shares legal information, not legal advice.