Law library · Sierra Leone · 62 of the Environmental Protection Act, 2008, the Board hereby makes
Section 22, 62 of the Environmental Protection Act, 2008, the Board hereby makes
Status not yet checked62 of the Environmental Protection Act, 2008, the Board hereby makes, Sierra Leone
(1) Where an EIA, SIA or ESIA is returned to the applicantby the Board on the basis of inadequacy, the Board shall state its
reasons and indicate the steps required by the applicant to rectify
the inadequacy within a period of 21 days as specified in paragraph
(b) of subsection (2) of section 28 of the Act.
(2) Subject to sub-regulation (1), the application for an
environmental licence shall be held in abeyance until the required
rectification of the inadequacy has been made and the relevant
environmental or social management instruments have been
resubmitted.
(3) In the event that the necessary rectification of the
inadequacy referred to in sub-regulation (1) are not addressed or the
relevant document is not resubmitted within 21 days, the application
for an environmental licence shall lapse.
(4) The Board may agree to extend the deadline outlined
in sub-regulations (1) to (3) at its discretion on the basis of a
reasonable case for an extension submitted by the applicant.