(1) After receipt of the application documents for anenvironmental licence, the Executive Chairman or Authorised Officer
shall widely disseminate and distribute the documents to local
communities in order to raise awareness of its contents and seeks
comments thereto.
(2) The Executive Chairman or Authorised Officer shall
disseminate notice to the public and the local community of all
Category A, B and C projects through a variety of information outlets
including radio broadcasts, posting details of the Category A, B or C
project in local community, facilitate meetings with local community
groups or civil society groups.
(3) Members of the public and the local community shall
be given fourteen days from the date of the last dissemination of
information to submit written comments to the Executive Chairman or
Authorised Officer.
compile a comprehensive list of all comments received from public
consultation including details of the comments and who provided
the comments.
(5) All documents submitted to the Executive Chairman
or Authorised Officer as part of an application for an environmental
licence shall be reviewed by officers with the relevant technical skills,
discipline and experience.
(6) The documents referred to in sub-regulation (1),
together with a report of the internal evaluation and list of public
comments prepared by an Executive Chairman or Authorised Officer
and endorsed by the Executive Chairman shall be submitted to the
Board at least five days prior to the Board meeting in which the issue
is to be addressed.
(7) The Board may, by simple majority decision, either-
(a) approve the documents and application and
request the Executive Chairman to grant an
environmental licence,
(b) conclude that there are inadequacies in the
assessments and return the application and
documents to the applicant with the option
of rectifying the inadequacies and
resubmitting them within 21 days.
(c) conclude that the scale of adverse environmental or social impacts is so great, and is
incapable of being avoided, mitigated or
compensated for, such that an environmental licence shall not be granted.
(8) The quorum of the Board for any decision to grant a
Category A or B environmental licence shall be two-thirds of appointed
members.
36 37
Inadequate
and social
assessments
Review of
licence
application
PART V – OBLIGATIONS OF AN ENVIRONMENTAL LICENCE
HOLDER
24 (1) The holder of an environmental licence shall prepare
an Environmental Management Plan and a Social Impact Management
Plan and shall -
(a) review the contents of such plans on each
anniversary of the commencement of works
(b) update the plans to accommodate any
changes that have occurred in the method of
mining, and area of operations, or other
activities that could affect environmental
protection and ultimate restoration or
rehabilitation of the affected areas .
(2) The holder of an environmental licence shall submit
an updated Environmental Management Plan and a Social
Management Plan to the Director of Mines and the Board within one
month of the anniversary of the commencement of works.