Ores Regulations, 2012
Status not yet checkedSubsidiary legislation · 10 provisions
Sign in to download the PDFAsk Tima about this lawCases on this law
Contents
- Preamble
- Section 1 — In these Regulations unless the context otherwise requires–
- Section 2
- Section 3
- Section 4
- Section 5
- Section 7
- Section 8 — (1) An application to operate a mine or mill shall include-
- Section 11
- Section 12
STATUTORY INSTRUMENT NO. 2 OF 2013
Published 7th March, 2013
THE PROTECTION FROM RADIATION Act, 2001
(Act No. 14 of 1991)
THE SAFETY IN MINING AND MILLING OF URANIUM AND OTHER
ORES REGULATIONS, 2012
IN EXERCISE of the powers conferred upon him by section 17
of the Protection from Radiation Act, 2001 and after consultation
with the Board, the Minister responsible for Energy and Water
Resources hereby makes these Regulations.
“backfill” means the placing of material (including
waste rock) into excavated portion of mine working;
“clean rock” means rock or overburden that does not
require regulatory control and can be considered a
resource for construction purposes or other net
benefit;
“clearance” means the removal of radioactive material
or radioactive objects within authorized practices
from any further control by the Board;
“community” means those people living in the area
which the activity may affect or which may generate
concern regarding health, environment, economic,
or cultural and social issues;
STATUTORY INSTRUMENT
Supplement to the Sierra Leone Gazette Vol. CXLIV, No. 11
dated 7th March, 2013
Short title.
I n t e r p r e t a -
tion
“decommissioning” means all steps leading to the
release of a facility, other than a disposal facility,
from regulatory control other than confirming the
decommissioned status of a facility including the
processes of decontamination, dismantling and site
rehabiltation;
“discharges” means planned and controlled releases
into the environment, as a legitimate practice, within
limits authorized by the Board of liquid or gaseous
material that originates from regulated facilities during
normal operation;
“disposal” means the emplacement of waste in an
approppriate facility without the intention of
retrieval;
“environmental values” means those aspects of the
ecosystem in which worth is placed by the
community or society because of their biodiversity,
aesthetic attributes, use for recreation or use as a
resource;
“exemption” means the determination by the Board
that a source or practice need not be subject to some
or all aspect of regulatory control on the basis that
the exposure (including potential exposure) due to
the source or practice is too small to warrant the
application of those aspects or, that this is the
optimum option for protection irrespective of the
actual level of doses or risks;
“hazardous substance” means a substance other than
a radioactive substance that is used or produced in
the course of carrying on a licensed activity and
that may pose a risk to the environment or the health
and saftety of people;
“in situ recovery” means operations to extract uranium
by means of chemical dissolution and liquid pumping
systems without physically disturbing the ore body;
intrusive exploration” means mechanized sampling of
the surface and subsurface geological structures for
the purpose of bulk sampling, by drilling, trenching
or coring or underground mining operations, and
requires surface access to the potential uranium
mineralized target area including pilot or
development testing;
“ionizing radiation” for the purpose of radiation
protection, means radiation capable of producing
ion pairs in biological materials;
“licence” means a legal document issued by the Board
granting authorization to perform specified activities
related to a facility or activity;
(1) These regulations shall apply to intrusive exploration,siting, of construction, operation and decommissioning of mining
and processing of uranium and processing of heavy mineral sands,
mining and processing of rare earth elements, mining ores other than
uranium and heavy mineral sands, production of oil and gas,
manufacture of titanium dioxide pigment, the phosphate industry,
the zircon and zirconia industry, production of tin, tantalum, copper,
aluminum, iron and steel and geothermal energy generation.
(2) Nothing in these Regulations shall be construed as
relieving any person from complying with any applicable law
governing safety, health and protection of workers, the public and
the environment.
Scope.
2 3
For the purposes of these Regulations, a radiationprotection plan shall include–
(a) (i) in den tifica tion of sources of ionionizing radiation, associated exposur e pathwa ys an d assessment
of radiation risks;
(ii) the design, engineering and administrative controls to optimize protecion measure and ensure compliance
with the established dose limits;
(iii) the health and safety training program,
that includes radiation protection, for
workers;
(iv) a medical health surveillance program,
that responds to the potential health
and safety risk posed by the activity;
and
(v) arrangements for monitoring, reviewing
reporting and recording the radiation exposure of workers.
(b) environmental management plan which
include–
(i) the environmental protection policies
and programs that will ensure environmentally sustainable development during design, construction, operation decommissioning and post-closure activities;
(ii) measures to prevent, limit and control
releases of radioactive and hazardous
substances (whether solid, liquid or
gas) to the environment;
(iii) identification of the potentially impacted
ecosyetems, resources and the environmental values to be protected and an
assessment of the associated risks;
(iv) the proposed location of authorized releases of radioactive substances and
hazardous substance into the environment, including their physical chemical
and radiological characteristics;
(v) the effect on the environment that may
result from the activity to be licensed
and the measures that will be taken to
prevent or mitigate the risks of those
effects;
(vi) the measure to prevent and mitigate the
effects of accidental releases of radioactive material and hazardous subtances on the environment;
(vii) the environmental quality objectives to
be achieved, with environmrntal outcomes and performance measures;
(viii) the environmental monitoring program
including baseline or pre-operational
monitoring;
(ix) the discharge quality objectives to be
achieved;
(x) the discharge monitoring program; and
(xi) measures to continuously improve environmental performance.
(c) a waste management program shall include–
4 5
Radiation
protection
plan.
(i) measures to ensure that the generation
of waste is kept to the minimum
practicable;
(ii) categorization of all wastes and identification of associated management system:
(iii) characteristics of all waste streams including tailing, waste rock and industrial waste;
(iv) consideration of radiological and nonradiological hazards, feasible management options (including backfill into
mine workings)
(v) definition of criteria and protocols to
segregate waste into appropriate categories including those used to identify
clean rock;
(vi) a description of the design and schedule
for the construction, operation and decommissioning of the waste management system including handling transport, temporary storage and final disposal and a risk assessment of and justification for selected management options; and
(vii) a safety assessment of the waste management system including accidental
situations and long term safety.
(d) a strategic management plan which shall
include–
(i) a recognized quality management
process;
(ii) a commitment to maintenance of an
acceptable safety culture;
(iii) incorporation of sustainable development principles into decision making
processes;
(iv) description of risk assessment and risk
management processes used by the organization;
(v) demonstration of adequate expertise,
human resources and financial resoures;
(vi) an organizational management structure that includes allocation of functions, responsibilities and authorities;
(vii) a program for self-assessment and audit
against regulatory requirements;
(viii) a program for regular review of radiation
environment and waste management
plans and their implementation; and
(ix) a program for independent verification
of radiation, environmental and waste
management plans and their simplementation.
(e) a community engagement plan which shall
include–
(i) a public information program which requires effective communication to the
community on the nature of the effects
of the activity or practice, on the environmental and the health and safety of
of persons which shall cover routine
and non-routine releases to the environment, environmental monitoring reports,
unplanned events, emergencies and any
other situations in which the community
has an interest.
6 7
(ii) commitment to openness and transparency including the timely release and
maximum disclosure of relevant informantion; and
(iii) commitment to consultation and engagement with all affected parties on the assessment and control of all significant
health, safety, environment, social, cultural and economic impacts of operations.
A company which wishes to conduct intrusive miningactivity shall apply to the Board for a licence.
(2) The application shall include-
(a) the applicant’s name and address
(b) a general description of the proposed activity
and the schedule;
(c) a description of the location of the proposed
activity including access to the site;
(b) a description of the proposed methods for
undertaking the activity;
(e) a list of the categories of material proposed
to be explored for;
(f) the plans for radiation protection and
environmental and waste management that
comply with regulation 3; and
(g) a site remediation and restoration plan.
(1) A company which wishes to construct a mine or millshall apply to the Board for a licence.
(2) The application shall include–
(b) a general description of the location
including, a surface plan which indicates the
boundaries of the mine or milling facility and
the area where the activity to be licensed is
proposed to be under taken;
(c) the proposed activities and their schedule;
(d) the radiation protection plan and the
environment management plan that comply
with regulation 3.
(e) a strategic management plan that complies
with regulation 3.
(f) a community engagement plan that complies
with regulation 3.
(g) a general description of the site’s geology
and mineralogy and the geotechnical
characteristics that influenced the design of
the mine or mill;
(h) the design details for the mine or mill
including the proposed installations or
structures, excavations, underground
working, open pit development or in situital
recovery developments planned;
(i) the results of a process hazard analysis or
safety analysis;
(j) the proposed decommissioning plan;
(k) initial de-commissioning plan for the activities
to be undertaken;
(l) a financial guarantee of an amount that the
Board may determine;
8 9
Intrusive
Exploration.
Construction
of mines or
mills.
(m) a description and justification for the
proposed mining methods and programme;
(n) the components, systems and equipment
proposed to be installed at the mine including
their design and operating condition, and
(o) a description of the characterization and
management controls to identify and handle
the mine materials.
(6) An application for the construction of an underground
mine shall include the information in regulation 3 and the following:-
(a) the proposed ventilation methods and
equipment for controlling air quality; and
(b) the proposed maintenance and in-service
inspection programme for the ventilation
control system.
(1) A company which wishes to undertake an in situmining shall apply to the Board for a licence.
(2) The application shall include the information required
in regulation 3 and the following :-
(a) the characteristic geology of the mine;
(b) demonstration that groundwater impacts can
be managed or remedied;
(c) the location and depth of the injection,
recovery, monitoring and waste disposal
wells;
(d) the proposed reporting of the extent and
movement of fluids and ground water
including monitoring and modelling;
(e) proposed reporting of impact of mining
operations on ground water; and
(f) location and depth of the installed injection,
recovery, monitoring and waste disposal
wells.
(b) a general description of the proposed
activities and their schedule;
(c) the results of a process-hazard analysis or
safety analysis;
(d) the proposed policies, methods and programs
for operating and maintaining the mine or
mill;
(e) a radiation protection plan that meets the
requirements of the Board;
(f) an environmental management plan that
meets the requirements of environmental
management plan in regulation 3,
(g) a waste management plan that meets the
requirements of waste management plan
in regulation 3;
(h) a strategic management plan that meets the
requirements of regulation 3;
(i) a community engagement plan that meets the
requirements of regulation 3,
(j) updates of the proposed decommissioning
plan, including commitments to ongoing
progressive rehabilitation;
(k) a financial guarantee of an amount to be
determined by the Board;
10 11
Underground
mines
In situ
recovery
mining.
Operation of
mine or mill.
(l) the ventilation, air quality management and
ground control plans;
(m) proposed reporting of the extent and
movement of mine fluids and groundwater
including monitoring and modeling;
(n) proposed reporting of impacts of mining
operations on groundwater, and
(o) location and depth of the installed injection,
recovery, monitoring and waste disposal
wells.
(9) An application to decommission a mine or mill shall include-
(b) a decommissioning plan that includes-
(i) the scope of the proposed decommissioning including land,
buildings, structures, components,
systems, equipment, waste materials,
radioactive materials and hazardous
substances that will be affected.
(ii) the scope of the currently authorized
mine or mill that will not be subject to
decommissioning;
(c) the term of the proposed authorization to
include the periods of active decommissioning work and ongoing institutional
control;
(d) the methods and programmes for carrying out
the decommissioning;
(e) schedules including proposals to
progressively apply for authorization to
release parts of the authorized mine or mill
from regulatory control;
(f) a radiation protection plan, environmental
management plan, a waste management plan
and a strategic management plan that meets
the requirement of regulation 3;
(g) a community engagement plan that meets the
requirement of regulation 3;
(h) a financial guarantee of an amount
determined by the Board;
(i) a safety case including an environmental
assessment to support the implementation
of the final decommissioning plan;
(j) the objectives and end-state status of the
authorized mine or mill on completion of
works;
(k) radiological and environmental criteria;
(l) performance measures and monitoring
programs that will demonstrate that the endstate criteria have been achieved;
(m) details of ongoing institutional controls
including access restriction and longterm
care and maintenance activities such as water
treatment;
(n) justification for any institutional controls;
(o) monitoring programs to demonstrate that
decommissioning objectives continue to be
achieved after the decommissioning phase
is completed;
(p) the content of records to be provided to the
Board at the conclusion of the term of the
authorization and location form and
accessibility of these records; and
12 13
Decommissioning.
(q) contingency measures to be taken if
decommissioning objectives do not continue
to be achieved,
(10) The application to release a mine or mill from regulatory
control shall include-
(b) the scope of the authorized site where
release from regulatory control is being
sought;
(c) a general description of the site and its
location, and any remaining buildings,
structures and equipment;
(d) results of decommissioning activities
including-
(i) radiation surveys;
(ii) environmental monitoring
(e) an assessment of the effectiveness of
rehabilitation works;
(f) structural assessment of engineered barriers;
(g) evidence that ongoing institutional controls
including access restrictions and long-term
case and maintenance activities such as water
treatment are in place and operating;
(h) location, form and accessibility of records
that have been retained;
(i) the updated safety case based on results of
decommisssioning activities;
(j) the proposed timing of release; and
(k) a community engagement plan that meets the
requirements of regulation 3.
(1) A licensee shall maintain primary responsibility forsafety and for ensuring compliance with all requirements in these
Regulations.
(2) The licensee shall-
(a) comply with the terms and conditions of the
licence;
(b) notify the Board of its intention to introduce
modifications to any practise for which it has
been licensed whenever the modification
could have significant implications for safety;
and shall not carry out the modification
unless specifically authorized by the Board;
(c) submit to the Board all routine reports that
are required by the Board; and in form
accepted to the Board;
(d) notify the Board as soon as practicable, but
not later than twenty four hours after
discovery of an accident or incident which
has the potential for or has resulted in
radiation doses in excess of the regulatory
limit or an unplanned environmental impact;
(e) submit to the Board within thirty days after
the initial notification referred to in paragraph
(d) a written report stating the cause of the
accident or incident and information on the
doses, corrective measures and any other
relevant information;
(f) notify the Board of any breach of their
authorization in a timely manner;
14 15
Release from
regulatory
control.
Responsibilities
of licensees.
(g) permit inspectors from the Board full access
to the authorized facility and such plans,
records, and information that are required to
be maintained by the licensee;
(h) ensure that the radiation level of all mineral
ores being exported are within the limits
determined by the Board;
(i) ensure that all tailings from ores are monitored
for radioactive contamination and those
above the limits determined by the Board
safely disposed of in the appropriate manner.
(1) Any licencee who fails to comply with any of theprovisions of these Regulations shall have the licence cancelled.
(2) Any person who commits an offence under these
regulations shall be liable to the penalties as established in the
enforcement policy issued by the Authority.
(3) The Authority shall impose an administrative fine, clause
of facility or any combination of these.
(4) Any person or corporate fine, closure of facility or any
combination of these.
(5) Any Licensee person may appeal to the Board if it is not
satisfied with the decision made against it pursuant to these
Regulations.
(13) The Board shall monitor the activities of its licensee to
ensure that these Regulations are complied with.
MADE this 29th day of October, 2012.
OLUNIYI ROBBIN–COKER,
Minister of Energy and Water Resource.
Cancellation
of licence.
PRINTED AND PUBLISHED BY THE GOVERNMENT PRINTING DEPARTMENT, SIERRA LEONE.
GAZETTE NO. 11 OF 7TH MARCH, 2013.
Inspection of
Mining sites.
Check the current official version before relying on this text. MiLAWYER shares legal information, not legal advice.